3353 S REDWOOD AVE 90066
Certificate Information: 3353 S REDWOOD AVE 90066
- Application / Permit
- 23014-30000-01502
- Plan Check / Job No.
- B23WL01012
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Bathroom addition to an (e) S.F.D. per WFPP.
- Permit Issued
- Issued on 5/25/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2023 | RICHARD GARCIA |
| Corrections Issued | 4/26/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 4/28/2023 | APPLICANT |
| Applicant returned to address corrections | 5/11/2023 | JOHNPAUL ISIP |
| Plan Check Approved | 5/25/2023 | JAHANSHAH POURHASSAN |
| Issued | 5/25/2023 | APPLICANT |
| CofO in Progress | 5/20/2025 | MICHAEL ALLEN |
| Permit Finaled | 5/20/2025 | RICHARD STEINBACH |
| CofO Issued | 5/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/21/2023 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2023 | DARIN LAM |
| Specific Plan | Cleared | 5/19/2023 | JOSHUA JONES |
| Roof/Waste drainage to street | Cleared | 5/22/2023 | DARIN LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/29/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 7/5/2023 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/11/2023 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 8/11/2023 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 8/23/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 8/29/2023 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/2/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/2/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 10/2/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/2/2023 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/2/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 10/5/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/5/2023 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 10/11/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 10/31/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/13/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 3/13/2025 | Approved | MICHAEL ALLEN |
| Final | 3/13/2025 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 3/13/2025 | Approved | MICHAEL ALLEN |
| HVAC-Final | 3/13/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 3/13/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 3/13/2025 | Approved | MICHAEL ALLEN |
| Final | 5/14/2025 | Partial Approval | MICHAEL ALLEN |
| Final | 5/19/2025 | OK to Issue CofO | MICHAEL ALLEN |