3254 S COLBY AVE 90066

Certificate Information: 3254 S COLBY AVE 90066

Application / Permit
23014-30000-01236
Plan Check / Job No.
B23WL00856
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
major remodel to 1st floor of (e) S.F.R. (1-wall to remain) and addition of 2nd story and attached garage.
Permit Issued
Issued on 3/14/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2023 APPLICANT
Assigned to Plan Check Engineer 4/19/2023 KAVIAN REFAHI
Corrections Issued 4/23/2023 KAVIAN REFAHI
Quality Review Completed 4/24/2023 CHIHARU SUZUKI
Building Plans Picked Up 4/25/2023 APPLICANT
Applicant returned to address corrections 3/6/2024 KAVIAN REFAHI
Plan Check Approved 3/11/2024 KAVIAN REFAHI
Issued 3/14/2024 APPLICANT
CofO in Progress 9/29/2025 KIRK SANDERS
Permit Finaled 10/15/2025 RICHARD STEINBACH
CofO Issued 10/15/2025 RICHARD STEINBACH
Permit Finaled 10/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 12/28/2023 BRENDEN HAWK
Trees in Parkway Cleared 2/15/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 2/16/2024 TOMMY YIN
Eng Process Fee Ord 176,300 Cleared 2/20/2024 DARIN LAM
Roof/Waste drainage to street Cleared 2/20/2024 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 2/20/2024 DARIN LAM
GPI Written Notices Cleared 3/6/2024 KAVIAN REFAHI
Grading Pre-Inspection Cleared 3/6/2024 KAVIAN REFAHI

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Zepeda Juan; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/6/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 5/6/2024 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 5/8/2024 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 5/8/2024 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 5/16/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 5/16/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 7/19/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 8/6/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 8/6/2024 Approved JESUS PINEDA
PLUMBING-Rough 8/8/2024 Corrections Issued JESUS PINEDA
Sewer 8/8/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 8/16/2024 Approved JESUS PINEDA
Underground Mechanical 8/16/2024 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 8/16/2024 Approved JESUS PINEDA
Green Building Rough 8/23/2024 Approved DANIEL VERA
Interior/Exterior Lathing 8/23/2024 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 9/4/2024 Partial Approval DANIEL VERA
Insulation 9/10/2024 Partial Approval DANIEL VERA
Wood Frame 9/10/2024 Approved DANIEL VERA
Drywall Nailing 9/16/2024 Approved DANIEL VERA
Shower Pan 10/3/2024 Approved DANIEL VERA
Interior/Exterior Lathing 10/9/2024 Partial Approval DANIEL VERA
Interior/Exterior Lathing 11/14/2024 Approved REGINA MENDEZ
Interior/Exterior Lathing 1/14/2025 Approved DANIEL VERA
Shower Pan 1/14/2025 Approved DANIEL VERA
Gas Test 4/9/2025 Approved WILBER ROSALES
ELECTRICAL-Final 4/14/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 4/14/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 4/14/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 4/21/2025 Approved WILBER ROSALES
PLUMBING-Final 4/21/2025 Corrections Issued WILBER ROSALES
Smoke Detectors 4/21/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/28/2025 Approved WILBER ROSALES
Final 4/28/2025 Not Ready for Inspection WILBER ROSALES
Green Building Final 4/28/2025 Not Ready for Inspection WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Approved WILBER ROSALES
ELECTRICAL-Final 6/11/2025 Approved WILBER ROSALES
Final 6/11/2025 Corrections Issued WILBER ROSALES
Green Building Final 6/11/2025 Approved WILBER ROSALES
PLUMBING-Final 6/11/2025 Approved WILBER ROSALES
Final 9/29/2025 OK to Issue CofO KIRK SANDERS
Service/Power Release 9/29/2025 Approved KIRK SANDERS