3557 S BARRINGTON AVE 90066

Certificate Information: 3557 S BARRINGTON AVE 90066

Application / Permit
23014-30000-01216
Plan Check / Job No.
B23WL00828
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2-story addition to (e) single story SFD w./ att. 2-car garage
Permit Issued
Issued on 9/5/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2023 APPLICANT
Assigned to Plan Check Engineer 4/19/2023 REZA HAGHIGHAT
Corrections Issued 4/23/2023 REZA HAGHIGHAT
Quality Review Completed 4/27/2023 KAVIAN REFAHI
Building Plans Picked Up 8/2/2023 APPLICANT
Plan Check Approved 8/22/2023 REZA HAGHIGHAT
Issued 9/5/2023 APPLICANT
CofO in Progress 5/15/2024 JESUS PINEDA
Permit Finaled 5/17/2024 DANIEL ORRANTE
CofO Issued 5/17/2024 DANIEL ORRANTE
Permit Finaled 5/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/7/2023 ROGELIO CORTES
Permit Cleared 8/7/2023 JASON NG
Roof/Waste drainage to street Cleared 8/7/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 8/9/2023 JASON NG
Sewer availability Cleared 8/9/2023 JASON NG
Trees in Parkway Cleared 8/21/2023 ADALBERTO VERA
GPI Written Notices Cleared 8/22/2023 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 8/22/2023 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Vip Construction 1 Inc; Lic. No.: 1097925-B 11038 BENWELL DRIVE APT D      LYNWOOD, CA 90262
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/13/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 9/18/2023 Partial Approval RICHARD STEINBACH
Deputy Drilled-In Anchors 9/26/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/27/2023 Partial Approval RICHARD STEINBACH
Deputy Steel/Welding 10/17/2023 Conditional Approval JESUS PINEDA
Deputy Wood Construction 10/24/2023 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval JESUS PINEDA
Special/Order Compliance 10/24/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval JESUS PINEDA
Deputy Wood Construction 12/1/2023 Conditional Approval MICHAEL PELHAM
Deputy Wood Construction 12/4/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 12/4/2023 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Approved JESUS PINEDA
HVAC-Rough 12/4/2023 Corrections Issued JESUS PINEDA
Interior/Exterior Lathing 12/4/2023 Approved JESUS PINEDA
PLUMBING-Rough 12/4/2023 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 12/6/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 12/6/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 12/6/2023 Approved JESUS RODRIGUEZ
Shower Pan 12/6/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 12/7/2023 No Access for Inspection KENNETH NAGLE
Green Building Rough 12/7/2023 No Access for Inspection KENNETH NAGLE
Verify Sprinkler Sign Off 12/7/2023 No Access for Inspection KENNETH NAGLE
Interior/Exterior Lathing 12/13/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 12/14/2023 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 12/14/2023 Corrections Issued JESUS PINEDA
Green Building Rough 12/14/2023 Not Ready for Inspection JESUS PINEDA
Verify Sprinkler Sign Off 12/14/2023 Not Ready for Inspection JESUS PINEDA
BUILDING-Rough-Frame 12/20/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 12/20/2023 Approved JESUS PINEDA
Green Building Rough 12/20/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 12/20/2023 Approved JESUS PINEDA
Verify Sprinkler Sign Off 12/20/2023 Approved JESUS PINEDA
Insulation 12/26/2023 Approved BEN MOLSTAD
Drywall Nailing 1/2/2024 Approved JESUS PINEDA
Gas Test 4/4/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 5/10/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 5/10/2024 Approved JESUS PINEDA
HVAC-Final 5/10/2024 Approved JESUS PINEDA
ELECTRICAL-Final 5/13/2024 Approved JESUS PINEDA
Final 5/13/2024 Corrections Issued JESUS PINEDA
Green Building Final 5/13/2024 Approved JESUS PINEDA
PLUMBING-Final 5/13/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/13/2024 SGSOV Approved JESUS PINEDA
Service/Power Release 5/13/2024 Approved JESUS PINEDA
Smoke Detectors 5/13/2024 Approved JESUS PINEDA
Final 5/15/2024 OK to Issue CofO JESUS PINEDA