561 N MOUNT HOLYOKE AVE 90272

Certificate Information: 561 N MOUNT HOLYOKE AVE 90272

Application / Permit
23014-30000-01187
Plan Check / Job No.
B23WL00811
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2-story with 1-level basement addition to (e) single story SFD w./ att. 3-car garage
Permit Issued
Issued on 10/2/2023
Issuing Office
West Los Angeles
Current Status
Issued on 10/2/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/28/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 REZA HAGHIGHAT
Corrections Issued 4/8/2023 REZA HAGHIGHAT
Quality Review Completed 4/11/2023 CHIHARU SUZUKI
Building Plans Picked Up 4/11/2023 APPLICANT
Applicant returned to address corrections 7/11/2023 REZA HAGHIGHAT
Plan Check Approved 9/21/2023 REZA HAGHIGHAT
Issued 10/2/2023 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/17/2023 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2023 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2023 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2023 DINAH GARIN
BHO/Hillside ordinance Cleared 4/17/2023 DINAH GARIN
Permit Cleared 4/17/2023 DINAH GARIN
Sewer availability Cleared 4/17/2023 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/28/2023 DINAH GARIN
Hydrant and Access approval Cleared 4/28/2023 MATTHEW CRAIG
Coastal Zone Cleared 5/16/2023 MAYELA VILLA
Miscellaneous Cleared 5/16/2023 MAYELA VILLA
Miscellaneous Cleared 5/16/2023 MAYELA VILLA
Excavation more than 5-ft deep Cleared 7/11/2023 CALOSHA APPROVED
GPI Written Notices Cleared 7/11/2023 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 7/11/2023 REZA HAGHIGHAT
Trees in Parkway Cleared 7/19/2023 ADALBERTO VERA
Low Impact Development (LID) Cleared 9/11/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/13/2023 AHMED AMARRAGY

Contact Information

Contractor Minardos Construction & Associates; Lic. No.: 728956-B 8758 VENICE BLVD STE 200      LOS ANGELES, CA 90405
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010
Engineer Wavering,, Derek; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784
Geologist Daugherty,, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 1/25/2024 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 1/30/2024 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 2/14/2024 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 2/16/2024 No Access for Inspection KENNETH NAGLE
Deputy Reinf. Concrete 3/1/2024 Conditional Approval EVAN COOPER
PLUMBING-Rough 3/18/2024 Partial Approval EVAN COOPER
PLUMBING-Rough 4/17/2024 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 5/2/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 5/6/2024 Partial Approval ARAM AVEDISIAN
Deputy Reinf. Concrete 5/7/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 6/5/2024 Partial Approval EVAN COOPER
Deputy Shotcrete 6/6/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 6/20/2024 Partial Approval EVAN COOPER
Deputy Steel/Welding 7/9/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 8/14/2024 Partial Approval EVAN COOPER
Deputy Reinf. Concrete 8/15/2024 Partial Approval EVAN COOPER
Deputy Steel/Welding 8/21/2024 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 8/21/2024 Partial Approval EVAN COOPER
Footing/Foundation/Slab 8/29/2024 Partial Approval EVAN COOPER
ELECTRICAL-Rough 9/4/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 9/4/2024 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 9/12/2024 Partial Approval EVAN COOPER
Footing/Foundation/Slab 9/18/2024 Approved EVAN COOPER
Deputy Reinf. Concrete 9/19/2024 Conditional Approval EVAN COOPER
Deputy Drilled-In Anchors 11/12/2024 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 11/19/2024 Conditional Approval EVAN COOPER
Underground Mechanical 11/21/2024 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 12/3/2024 Approved EVAN COOPER
Footing/Foundation/Slab 12/3/2024 Approved EVAN COOPER
PLUMBING-Rough 9/25/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 9/30/2025 Partial Approval STEPHANIE SWANSON
Special/Order Compliance 9/30/2025 Partial Inspection KENNETH NAGLE
ELECTRICAL-Rough 11/24/2025 Partial Approval KENNETH NAGLE
PLUMBING-Rough 11/24/2025 Partial Approval KENNETH NAGLE
Deputy Steel/Welding 12/11/2025 Conditional Approval STEPHANIE SWANSON
Deputy Steel/Welding 12/12/2025 Conditional Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/17/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Partial Approval STEPHANIE SWANSON
Deputy Steel/Welding 1/29/2026 Conditional Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/31/2026 Partial Approval STEPHANIE SWANSON
Sewer 3/31/2026 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/8/2026 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/26/2026 Corrections Issued STEPHANIE SWANSON