6931 N WOODLAKE AVE 91307

Certificate Information: 6931 N WOODLAKE AVE 91307

Application / Permit
23014-30000-01125
Plan Check / Job No.
B23VN02945
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) garage and addition to (N) ADU per Ordinance a LAMC 12.22 A.33 C -D School fees combined and charged in one permit 23014-20000-00908 only ( 460 sft +435 sft for adu ) and (335 sft for SFD )
Permit Issued
Issued on 6/21/2023
Issuing Office
Current Status
Issued on 6/21/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/10/2023 APPLICANT
Assigned to Plan Check Engineer 3/16/2023 YASHAR EMAMI
Corrections Issued 3/23/2023 YASHAR EMAMI
Quality Review Completed 3/28/2023 CHIHARU SUZUKI
Applicant returned to address corrections 5/18/2023 YASHAR EMAMI
Plan Check Approved 6/16/2023 YASHAR EMAMI
Issued 6/21/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/4/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 4/5/2023 NIKKI ZULUETA
Sewer availability Cleared 4/5/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 4/28/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/6/2023 NIKKI ZULUETA

Contact Information

Contractor William Brothers Building & Construction; Lic. No.: 1063461-B 15720 VENTURA BLVD #616      ENCINO, CA 91436
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/3/2023 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 8/10/2023 Approved TROY SANDERS
Footing/Foundation/Slab 8/10/2023 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Partial Approval TROY SANDERS
PLUMBING-Rough 8/16/2023 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 9/18/2023 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Approved JEFFREY HARTLINE
Green Building Rough 9/18/2023 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 9/28/2023 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 9/28/2023 Approved MORRIS JACKSON
Green Building Rough 9/28/2023 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 9/28/2023 Approved MORRIS JACKSON
PLUMBING-Rough 9/28/2023 Approved MORRIS JACKSON
Underground Mechanical 9/28/2023 Approved MORRIS JACKSON
Wood Frame 9/28/2023 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 10/25/2023 Approved MORRIS JACKSON
Insulation 10/25/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/25/2023 Partial Approval MORRIS JACKSON
Drywall Nailing 11/2/2023 Approved TROY SANDERS
Gas Test 7/11/2024 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 4/8/2025 Approved TROY SANDERS
Final 4/8/2025 Corrections Issued TROY SANDERS
Green Building Final 4/8/2025 Not Ready for Inspection TROY SANDERS
Green Building Rough 4/8/2025 Approved TROY SANDERS
Smoke Detectors 4/8/2025 Approved TROY SANDERS