768 W 138TH ST 90247

Certificate Information: 768 W 138TH ST 90247

Application / Permit
23014-30000-01034
Plan Check / Job No.
B23WL00699
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
Addition of 9' x 18'-9" playroom to the back of the detached garage in the rear of the lot accessory to a SFD per WFPP
Permit Issued
Issued on 7/5/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2023 APPLICANT
Assigned to Plan Check Engineer 3/17/2023 JAHANSHAH POURHASSAN
Corrections Issued 3/17/2023 JAHANSHAH POURHASSAN
Plan Check Approved 7/3/2023 AMY GUEVARRA
Issued 7/5/2023 APPLICANT
CofO in Progress 5/24/2024 ANSON MAGLASANG
Permit Finaled 5/24/2024 ANSON MAGLASANG
CofO Issued 5/24/2024 ANSON MAGLASANG
Permit Finaled 5/24/2024 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/20/2023 CINDY QI
Roof/Waste drainage to street Cleared 3/20/2023 CINDY QI
Sewer availability Cleared 3/20/2023 CINDY QI
Construction near power lines Cleared 6/20/2023 RIDWAN HARDY

Contact Information

Contractor Waler Co; Lic. No.: 730835-B 11472 BROADMEAD STREET      SOUTH EL MONTE, CA 91733
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/7/2023 Partial Approval JAMES CHAVEZ
Sewer 8/7/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 8/17/2023 Not Ready for Inspection JAMES CHAVEZ
METHANE-Barrier 8/17/2023 Not Ready for Inspection JAMES CHAVEZ
METHANE-Subgrade 8/17/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 8/22/2023 Approved JAMES CHAVEZ
METHANE-Barrier 8/22/2023 Approved JAMES CHAVEZ
METHANE-Subgrade 8/22/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 10/12/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 10/12/2023 Approved JAMES CHAVEZ
Green Building Rough 10/12/2023 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 10/12/2023 Approved JAMES CHAVEZ
METHANE-Rough 10/12/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 10/12/2023 Approved JAMES CHAVEZ
Insulation 10/31/2023 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 10/31/2023 Partial Approval JAMES CHAVEZ
Insulation 11/7/2023 Approved JOHN KLARIN
Drywall Nailing 11/14/2023 Corrections Issued JOHN KLARIN
Green Building Rough 11/14/2023 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 11/17/2023 Approved JAMES CHAVEZ
Green Building Rough 11/17/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 12/18/2023 Approved JOHN KLARIN
Final 12/18/2023 Corrections Issued JOHN KLARIN
Green Building Final 12/18/2023 Approved JOHN KLARIN
MERV13>=Final 12/18/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 12/18/2023 Approved JOHN KLARIN
Final 1/3/2024 Corrections Issued JOHN KLARIN
Final 5/24/2024 OK to Issue CofO ANSON MAGLASANG