2721 S VETERAN AVE 90064
Certificate Information: 2721 S VETERAN AVE 90064
- Application / Permit
- 23014-30000-01011
- Plan Check / Job No.
- B23WL00685
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Detached garage/storage conversation into ADU
- Permit Issued
- Issued on 2/21/2025
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2023 | KAVIAN REFAHI |
| Corrections Issued | 3/25/2023 | KAVIAN REFAHI |
| Quality Review Completed | 3/28/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 4/12/2023 | APPLICANT |
| Applicant returned to address corrections | 6/10/2024 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/24/2024 | KAVIAN REFAHI |
| Plan Check Approved | 8/20/2024 | KAVIAN REFAHI |
| Issued | 2/21/2025 | APPLICANT |
| CofO in Progress | 3/18/2026 | ARAM AVEDISIAN |
| Permit Finaled | 3/18/2026 | RICHARD STEINBACH |
| CofO Issued | 3/18/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/18/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/23/2023 | RIDWAN HARDY |
| Address approval | Cleared | 6/2/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2023 | DINAH GARIN |
| Sewer availability | Cleared | 6/7/2023 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/24/2024 | KAVIAN REFAHI |
| Specific Plan | Cleared | 8/14/2024 | JOSHUA JONES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shirley,, Peter; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 3/19/2025 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 3/25/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 3/25/2025 | Not Ready for Inspection | KIRK SANDERS |
| Underground Mechanical | 3/25/2025 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 3/27/2025 | Conditional Approval | ARAM AVEDISIAN |
| Underground Mechanical | 4/3/2025 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 4/8/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/24/2025 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/28/2025 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 4/28/2025 | Conditional Approval | KIRK SANDERS |
| Final | 4/28/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/28/2025 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 4/29/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/2/2025 | Partial Approval | WILBER ROSALES |
| ELECTRICAL-Rough | 5/2/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 5/2/2025 | Approved | WILBER ROSALES |
| HVAC-Rough | 5/2/2025 | Partial Approval | WILBER ROSALES |
| PLUMBING-Rough | 5/2/2025 | Approved | WILBER ROSALES |
| Insulation | 5/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/12/2025 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 6/5/2025 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 6/11/2025 | Approved | ARAM AVEDISIAN |
| Shower Pan | 6/27/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 7/1/2025 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 7/1/2025 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 9/19/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/23/2025 | Conditional Approval | DANIEL VERA |
| ELECTRICAL-Final | 9/23/2025 | No Access for Inspection | DANIEL VERA |
| Final | 9/23/2025 | No Access for Inspection | DANIEL VERA |
| Green Building Final | 9/23/2025 | No Access for Inspection | DANIEL VERA |
| HVAC-Final | 9/23/2025 | No Access for Inspection | DANIEL VERA |
| MERV13>=Final | 9/23/2025 | No Access for Inspection | DANIEL VERA |
| MERV13>=Rough | 9/23/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 9/23/2025 | No Access for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Not Ready | DANIEL VERA |
| Smoke Detectors | 9/23/2025 | No Access for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 9/23/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 9/25/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 9/25/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 9/25/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/10/2025 | No Access for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 10/10/2025 | No Access for Inspection | KIRK SANDERS |
| Final | 10/10/2025 | No Access for Inspection | KIRK SANDERS |
| Green Building Final | 10/10/2025 | No Access for Inspection | KIRK SANDERS |
| HVAC-Final | 10/10/2025 | Not Ready for Inspection | KIRK SANDERS |
| MERV13>=Final | 10/10/2025 | No Access for Inspection | KIRK SANDERS |
| PLUMBING-Final | 10/10/2025 | No Access for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 10/10/2025 | No Access for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 10/20/2025 | Approved | KIRK SANDERS |
| Final | 10/20/2025 | Corrections Issued | KIRK SANDERS |
| Gas Test | 10/20/2025 | Approved | KIRK SANDERS |
| Green Building Final | 10/20/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 10/20/2025 | Partial Approval | KIRK SANDERS |
| MERV13>=Final | 10/20/2025 | Approved | KIRK SANDERS |
| PLUMBING-Final | 10/20/2025 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 10/20/2025 | Approved | KIRK SANDERS |
| Final | 3/18/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 3/18/2026 | Approved | ARAM AVEDISIAN |