1640 N GARDNER ST 90046
Certificate Information: 1640 N GARDNER ST 90046
- Application / Permit
- 23014-30000-00977
- Plan Check / Job No.
- B23WL00654
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Renovation of 2 baths, subtraction of 154 sf, addition of 53 sf plus 2 new ext. doors and 1 new ext. window at rear of house.
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2023 | RICHARD GARCIA |
| Corrections Issued | 3/23/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 3/28/2023 | APPLICANT |
| Plan Check Approved | 4/17/2023 | RICHARD GARCIA |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 10/20/2023 | STUART CHAPMAN |
| CofO in Progress | 10/24/2023 | STUART CHAPMAN |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| HPOZ | Cleared | 4/10/2023 | AMANDA KAINER |
| Roof/Waste drainage to street | Cleared | 4/10/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 4/10/2023 | TREVOR QUAN |
| ZI | Cleared | 4/10/2023 | AMANDA KAINER |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2023 | TREVOR QUAN |
Contact Information
| Architect | Griffin,, Margaret P; Lic. No.: C26524 | 1357 SUNSET AVENUE SANTA MONICA, CA 90405 |
| Contractor | Waterstone Construction And Development Inc; Lic. No.: 884762-B | P O BOX 1282 CULVER CITY, CA 90232 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/1/2023 | Conditional Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/6/2023 | No Access for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/6/2023 | No Access for Inspection | RAUL BARAJAS |
| HVAC-Rough | 6/6/2023 | No Access for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 6/6/2023 | No Access for Inspection | RAUL BARAJAS |
| Wood Frame | 6/6/2023 | No Access for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/9/2023 | No Access for Inspection | RAUL BARAJAS |
| HVAC-Rough | 6/9/2023 | No Access for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 6/9/2023 | No Access for Inspection | RAUL BARAJAS |
| Wood Frame | 6/9/2023 | No Access for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 6/12/2023 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 6/12/2023 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 6/12/2023 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/15/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/3/2023 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/3/2023 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 7/3/2023 | Approved | BRIAN SULLIVAN |
| Insulation | 7/3/2023 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/11/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 7/11/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/11/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/14/2023 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 7/14/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/14/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/7/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 8/7/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 8/7/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 8/7/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/11/2023 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/11/2023 | Approved | STUART CHAPMAN |
| Insulation | 8/11/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/11/2023 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 8/11/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/16/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/16/2023 | Approved | STUART CHAPMAN |
| Shower Pan | 8/16/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 10/6/2023 | Approved | RAUL BARAJAS |
| Final | 10/6/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 10/6/2023 | Conditional Approval | RAUL BARAJAS |
| HVAC-Final | 10/6/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 10/6/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 10/6/2023 | Approved | RAUL BARAJAS |
| Final | 10/12/2023 | Corrections Issued | STUART CHAPMAN |
| Final | 10/17/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 10/17/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 10/19/2023 | OK to Issue CofO | STUART CHAPMAN |
| Green Building Final | 10/19/2023 | Approved | STUART CHAPMAN |
| Final | 10/23/2023 | OK to Issue CofO | STUART CHAPMAN |
| Green Building Final | 10/23/2023 | Approved | STUART CHAPMAN |