1640 N GARDNER ST 90046

Certificate Information: 1640 N GARDNER ST 90046

Application / Permit
23014-30000-00977
Plan Check / Job No.
B23WL00654
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Renovation of 2 baths, subtraction of 154 sf, addition of 53 sf plus 2 new ext. doors and 1 new ext. window at rear of house.
Permit Issued
Issued on 5/5/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2023 APPLICANT
Assigned to Plan Check Engineer 3/23/2023 RICHARD GARCIA
Corrections Issued 3/23/2023 RICHARD GARCIA
Building Plans Picked Up 3/28/2023 APPLICANT
Plan Check Approved 4/17/2023 RICHARD GARCIA
Issued 5/5/2023 APPLICANT
CofO in Progress 10/20/2023 STUART CHAPMAN
CofO in Progress 10/24/2023 STUART CHAPMAN
CofO Issued 12/5/2023 DEROLD HAUFF
Permit Finaled 12/5/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 4/10/2023 AMANDA KAINER
Roof/Waste drainage to street Cleared 4/10/2023 TREVOR QUAN
Sewer availability Cleared 4/10/2023 TREVOR QUAN
ZI Cleared 4/10/2023 AMANDA KAINER
Eng Process Fee Ord 176,300 Cleared 4/11/2023 TREVOR QUAN

Contact Information

Architect Griffin,, Margaret P; Lic. No.: C26524 1357 SUNSET AVENUE      SANTA MONICA, CA 90405
Contractor Waterstone Construction And Development Inc; Lic. No.: 884762-B P O BOX 1282      CULVER CITY, CA 90232
Engineer Zangoli,, Fabio; Lic. No.: S6191 13245 FIJI WY UNIT J      MARINA DEL REY, CA 90292

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/1/2023 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 6/6/2023 No Access for Inspection RAUL BARAJAS
Footing/Foundation/Slab 6/6/2023 No Access for Inspection RAUL BARAJAS
HVAC-Rough 6/6/2023 No Access for Inspection RAUL BARAJAS
PLUMBING-Rough 6/6/2023 No Access for Inspection RAUL BARAJAS
Wood Frame 6/6/2023 No Access for Inspection RAUL BARAJAS
ELECTRICAL-Rough 6/9/2023 No Access for Inspection RAUL BARAJAS
HVAC-Rough 6/9/2023 No Access for Inspection RAUL BARAJAS
PLUMBING-Rough 6/9/2023 No Access for Inspection RAUL BARAJAS
Wood Frame 6/9/2023 No Access for Inspection RAUL BARAJAS
ELECTRICAL-Rough 6/12/2023 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/12/2023 Approved RAUL BARAJAS
HVAC-Rough 6/12/2023 Partial Approval RAUL BARAJAS
PLUMBING-Rough 6/12/2023 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 6/15/2023 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 7/3/2023 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 7/3/2023 Partial Approval BRIAN SULLIVAN
Green Building Rough 7/3/2023 Approved BRIAN SULLIVAN
Insulation 7/3/2023 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 7/11/2023 Not Ready for Inspection STUART CHAPMAN
Insulation 7/11/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/11/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/14/2023 Partial Approval STUART CHAPMAN
Drywall Nailing 7/14/2023 Partial Approval STUART CHAPMAN
Interior/Exterior Lathing 7/14/2023 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 8/7/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 8/7/2023 Approved STUART CHAPMAN
HVAC-Rough 8/7/2023 Approved STUART CHAPMAN
PLUMBING-Rough 8/7/2023 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 8/11/2023 Approved STUART CHAPMAN
Footing/Foundation/Slab 8/11/2023 Approved STUART CHAPMAN
Insulation 8/11/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/11/2023 Partial Approval STUART CHAPMAN
PLUMBING-Rough 8/11/2023 Approved STUART CHAPMAN
BUILDING-Rough-Frame 8/16/2023 Approved STUART CHAPMAN
Drywall Nailing 8/16/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/16/2023 Approved STUART CHAPMAN
Shower Pan 8/16/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 10/6/2023 Approved RAUL BARAJAS
Final 10/6/2023 Corrections Issued RAUL BARAJAS
Green Building Final 10/6/2023 Conditional Approval RAUL BARAJAS
HVAC-Final 10/6/2023 Approved RAUL BARAJAS
PLUMBING-Final 10/6/2023 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 10/6/2023 SGSOV Approved RAUL BARAJAS
Smoke Detectors 10/6/2023 Approved RAUL BARAJAS
Final 10/12/2023 Corrections Issued STUART CHAPMAN
Final 10/17/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 10/17/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 10/19/2023 OK to Issue CofO STUART CHAPMAN
Green Building Final 10/19/2023 Approved STUART CHAPMAN
Final 10/23/2023 OK to Issue CofO STUART CHAPMAN
Green Building Final 10/23/2023 Approved STUART CHAPMAN