11417 W BARMAN ST 90230

Certificate Information: 11417 W BARMAN ST 90230

Application / Permit
23014-30000-00911
Plan Check / Job No.
B23LA02916
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
eplan. storage addition to existing 2-car garage. ** 2 of 2 **
Permit Issued
Issued on 5/16/2023
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2023 APPLICANT
Assigned to Plan Check Engineer 3/2/2023 KAVIAN REFAHI
Corrections Issued 3/7/2023 KAVIAN REFAHI
Quality Review Completed 3/9/2023 CHIHARU SUZUKI
Applicant returned to address corrections 3/30/2023 KAVIAN REFAHI
Applicant returned to address corrections 4/25/2023 KAVIAN REFAHI
Plan Check Approved 5/11/2023 KAVIAN REFAHI
Plan Check Approved 5/16/2023 KAVIAN REFAHI
No Progress 5/16/2023 KAVIAN REFAHI
Plan Check Approved 5/16/2023 KAVIAN REFAHI
Issued 5/16/2023 APPLICANT
CofO in Progress 8/24/2023 JESUS RODRIGUEZ
Permit Finaled 8/29/2023 DANIEL ORRANTE
CofO Issued 8/29/2023 DANIEL ORRANTE
Permit Finaled 8/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/21/2023 JENSON LEE
Roof/Waste drainage to street Cleared 3/21/2023 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 5/22/2023 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/22/2023 Approved JESUS RODRIGUEZ
Green Building Rough 5/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
MERV13>=Rough 5/22/2023 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 6/30/2023 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Final 6/30/2023 Approved JESUS RODRIGUEZ
Final 6/30/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 6/30/2023 Approved JESUS RODRIGUEZ
Green Building Rough 6/30/2023 Approved JESUS RODRIGUEZ
Service/Power Release 6/30/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/19/2023 Approved JESUS RODRIGUEZ
Final 7/19/2023 Corrections Issued JESUS RODRIGUEZ
Final 8/23/2023 Partial Approval JESUS RODRIGUEZ