736 E BROOKS AVE 90291
Certificate Information: 736 E BROOKS AVE 90291
- Application / Permit
- 23014-30000-00897
- Plan Check / Job No.
- B23WL00595
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 1-story addition (585 sf) to (e) single story SFD (780 sf) per DIR-2023-2075-CDP-MEL-HCA
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2023 | REZA HAGHIGHAT |
| Corrections Issued | 3/11/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 3/14/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 3/16/2023 | APPLICANT |
| Plan Check Approved | 8/5/2024 | REZA HAGHIGHAT |
| Issued | 8/8/2024 | APPLICANT |
| CofO in Progress | 8/27/2025 | MICHAEL ALLEN |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
| CofO Issued | 9/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 2/8/2024 | BRENDEN HAWK |
| Coastal Zone | Cleared | 4/12/2024 | ROSALINDA MEZA |
| Frnt yard landscape/Water mgmt | Cleared | 4/12/2024 | ROSALINDA MEZA |
| Specific Plan | Cleared | 4/12/2024 | ROSALINDA MEZA |
| ZA Case | Cleared | 4/23/2024 | ROSALINDA MEZA |
| ZA Case | Cleared | 4/23/2024 | ROSALINDA MEZA |
| Low Impact Development (LID) | Cleared | 6/7/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 6/16/2024 | BRENDEN HAWK |
| ZA Case | Cleared | 7/11/2024 | ROSALINDA MEZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/29/2024 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 11/1/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 11/1/2024 | Corrections Issued | HERBERT GIRON |
| Sewer | 11/1/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 11/4/2024 | Corrections Issued | HERBERT GIRON |
| Sewer | 11/4/2024 | Approved | HERBERT GIRON |
| Deputy Drilled-In Anchors | 11/26/2024 | Conditional Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 11/26/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 11/26/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 12/13/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 1/3/2025 | Partial Approval | JESUS PINEDA |
| Underground Mechanical | 1/3/2025 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Partial Approval | TEMISTOCLES CAAL |
| Insulation | 1/6/2025 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Approved | HERBERT GIRON |
| Deputy Reinf. Concrete | 2/28/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 2/28/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/10/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/10/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/10/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/18/2025 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 3/18/2025 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/18/2025 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 3/18/2025 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 3/24/2025 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 3/24/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Drywall Nailing | 4/2/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/7/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/20/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/20/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Service/Power Release | 6/20/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/27/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 6/27/2025 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/27/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 6/27/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 7/8/2025 | Approved | MICHAEL ALLEN |
| Final | 8/26/2025 | OK to Issue CofO | MICHAEL ALLEN |
| Green Building Final | 8/26/2025 | Approved | MICHAEL ALLEN |