3252 S GRANVILLE AVE 90066
Certificate Information: 3252 S GRANVILLE AVE 90066
- Application / Permit
- 23014-30000-00821
- Plan Check / Job No.
- B23WL00537
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- major remodel & addition to existing S.F.D., removing entire house w/ the exception of wall & foundation .
- Permit Issued
- Issued on 12/29/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2023 | KAVIAN REFAHI |
| Corrections Issued | 3/11/2023 | KAVIAN REFAHI |
| Quality Review Completed | 3/13/2023 | CHIHARU SUZUKI |
| Building Plans Picked Up | 3/15/2023 | APPLICANT |
| Applicant returned to address corrections | 9/26/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/27/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/31/2023 | KAVIAN REFAHI |
| Plan Check Approved | 11/21/2023 | KAVIAN REFAHI |
| Issued | 12/29/2023 | APPLICANT |
| CofO in Progress | 11/8/2024 | DANIEL VERA |
| CofO Issued | 11/13/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/13/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 9/21/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/22/2023 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 9/23/2023 | AHMED AMARRAGY |
| GPI Written Notices | Cleared | 10/31/2023 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 10/31/2023 | KAVIAN REFAHI |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Vip Construction 1 Inc; Lic. No.: 1097925-B | 11038 BENWELL DRIVE APT D LYNWOOD, CA 90262 |
| Engineer | Namdar,, Mansour; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/18/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 1/25/2024 | Partial Approval | JESUS PINEDA |
| Deputy Drilled-In Anchors | 1/31/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/31/2024 | Approved | JESUS PINEDA |
| Sewer | 1/31/2024 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 3/15/2024 | Conditional Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 4/5/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 4/5/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/5/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 4/5/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 4/12/2024 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 4/29/2024 | Partial Approval | JESUS PINEDA |
| Interior/Exterior Lathing | 5/16/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/21/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/22/2024 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 5/22/2024 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 5/22/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/23/2024 | Approved | JESUS PINEDA |
| Insulation | 5/23/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/31/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 9/23/2024 | Approved | DANIEL VERA |
| PLUMBING-Final | 9/23/2024 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 9/26/2024 | Approved | DANIEL VERA |
| HVAC-Final | 10/4/2024 | Corrections Issued | DANIEL VERA |
| Final | 10/8/2024 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 10/8/2024 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 10/8/2024 | Approved | ARAM AVEDISIAN |
| Final | 10/15/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 10/15/2024 | Approved | DANIEL VERA |
| Final | 11/8/2024 | OK to Issue CofO | DANIEL VERA |
| Service/Power Release | 11/8/2024 | Approved | DANIEL VERA |