751 S BEVERLY GLEN BLVD 90024

Certificate Information: 751 S BEVERLY GLEN BLVD 90024

Application / Permit
23014-30000-00820
Plan Check / Job No.
B23WL00535
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2-story addition to (e) single story SFD w./ att. 2-car garage
Permit Issued
Issued on 8/29/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2023 APPLICANT
Assigned to Plan Check Engineer 3/8/2023 REZA HAGHIGHAT
Corrections Issued 3/12/2023 REZA HAGHIGHAT
Quality Review Completed 3/14/2023 KAVIAN REFAHI
Building Plans Picked Up 3/15/2023 APPLICANT
Plan Check Approved 8/22/2023 REZA HAGHIGHAT
Issued 8/29/2023 APPLICANT
CofO in Progress 5/14/2025 DANIEL VERA
Permit Finaled 5/15/2025 RICHARD STEINBACH
CofO Issued 5/15/2025 RICHARD STEINBACH
Permit Finaled 5/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/26/2023 ROGELIO CORTES
Permit Cleared 8/10/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 8/14/2023 ANTHONY MAINEZ
Sewer availability Cleared 8/14/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 8/16/2023 ANTHONY MAINEZ
GPI Written Notices Cleared 8/22/2023 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 8/22/2023 REZA HAGHIGHAT

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 10/6/2023 Corrections Issued CHRISTOPHER WILSON
Sewer 10/6/2023 Off-Hour Fees Due
Underground Mechanical 10/6/2023 Off-Hour Fees Due
Sewer 10/7/2023 Off-Hour Fees Due
Underground Mechanical 10/7/2023 Off-Hour Fees Due
BUILDING-Rough-Frame 10/11/2023 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 10/11/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 10/11/2023 Conditional Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 10/13/2023 Corrections Issued STEPHANIE SWANSON
Pre-Inspection 11/7/2023 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 11/8/2023 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 11/15/2023 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Approved CARLOS MATAMOROS
PLUMBING-Rough 1/10/2024 Approved STEPHANIE SWANSON
Shower Pan 2/12/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 2/28/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 2/28/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 3/7/2024 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 3/7/2024 Corrections Issued STEPHANIE SWANSON
Final 3/7/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/7/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Approval STEPHANIE SWANSON
HVAC-Rough 4/5/2024 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 4/5/2024 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 4/11/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 4/11/2024 Approved STEPHANIE SWANSON
HVAC-Rough 4/11/2024 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 4/11/2024 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 4/11/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 4/18/2024 Not Ready for Inspection SEAN HAUPT
Insulation 4/18/2024 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 4/19/2024 Approved STEPHANIE SWANSON
Insulation 4/19/2024 Approved STEPHANIE SWANSON
Drywall Nailing 4/29/2024 Approved SEAN HAUPT
ELECTRICAL-Final 4/8/2025 Not Ready for Inspection DANIEL VERA
Final 4/8/2025 Not Ready for Inspection DANIEL VERA
Green Building Final 4/8/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 4/8/2025 Corrections Issued DANIEL VERA
PLUMBING-Final 4/8/2025 Not Ready for Inspection DANIEL VERA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Not Ready DANIEL VERA
Smoke Detectors 4/8/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 4/22/2025 Not Ready for Inspection DANIEL VERA
Final 4/22/2025 Corrections Issued DANIEL VERA
Green Building Final 4/22/2025 Not Ready for Inspection DANIEL VERA
HVAC-Final 4/22/2025 Not Ready for Inspection DANIEL VERA
PLUMBING-Final 4/22/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Not Ready DANIEL VERA
Smoke Detectors 4/22/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 4/24/2025 Partial Approval MEL KHACHATOURIAN
Service/Power Release 4/24/2025 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 4/25/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Final 4/29/2025 Approved DANIEL VERA
Final 4/29/2025 Corrections Issued DANIEL VERA
Green Building Final 4/29/2025 Approved DANIEL VERA
HVAC-Final 4/29/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Approved DANIEL VERA
Smoke Detectors 4/29/2025 Approved DANIEL VERA
Final 5/1/2025 Not Ready for Inspection DANIEL VERA
Service/Power Release 5/1/2025 Approved DANIEL VERA
Final 5/13/2025 OK to Issue CofO DANIEL VERA