1559-1561 N BUNDY DR 90049
Certificate Information: 1559-1561 N BUNDY DR 90049
- Application / Permit
- 23014-30000-00692
- Plan Check / Job No.
- B23WL00451
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) portion of Single Family dwelling to JADU per state law. Interior remodel of existing single story residence and removal of (E) carport and breezeway. new roof and roof framing, replacement of exterior doors and windows and addition. See comments
- Permit Issued
- Issued on 8/1/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2023 | JAHANSHAH POURHASSAN |
| Corrections Issued | 3/7/2023 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 3/8/2023 | APPLICANT |
| Applicant returned to address corrections | 10/19/2023 | SAMUEL GONZALEZ |
| Plan Check Approved | 12/14/2023 | DANIEL SANJUAN |
| No Progress | 12/21/2023 | DANIEL SANJUAN |
| Plan Check Approved | 2/13/2024 | DANIEL SANJUAN |
| Issued | 8/1/2024 | APPLICANT |
| CofO in Progress | 4/20/2026 | KEVIN SARGSYAN |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
| CofO Issued | 4/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/8/2023 | AHMED AMARRAGY |
| BHO/Hillside ordinance | Cleared | 5/8/2023 | AHMED AMARRAGY |
| BHO/Hillside ordinance | Cleared | 5/8/2023 | AHMED AMARRAGY |
| BHO/Hillside ordinance | Cleared | 5/8/2023 | AHMED AMARRAGY |
| Street Frontage | Cleared | 5/8/2023 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 5/9/2023 | HISASHI KOBAYAKAWA |
| Watercourse | Cleared | 5/9/2023 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2023 | BRENDEN HAWK |
| BHO/Hillside ordinance | Cleared | 10/16/2023 | BRENDEN HAWK |
| Address approval | Cleared | 1/18/2024 | DARIN LAM |
| Sewer availability | Cleared | 1/18/2024 | DARIN LAM |
Contact Information
| Architect | Desai,, Manish Mahesh; Lic. No.: C30479 | 169 1/2 SAN GABRIEL CT. SIERRA MADRE, CA 91024 |
| Contractor | Owner-Builder | , |
| Engineer | Hansen,, Neil Christian; Lic. No.: L9027 | 1545 VICTORY BLVD 2ND FLOOR N.C. HANSEN INC. GLENDALE, CA 91201 |
| Engineer | Mccullum,, Eric William; Lic. No.: C68850 | 727 2ND ST STE 104 HERMOSA BEACH, CA 90254 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/17/2024 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 9/19/2024 | Conditional Approval | CASIMIR BRITTON |
| Footing/Foundation/Slab | 9/25/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/20/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2024 | Conditional Approval | ARAM AVEDISIAN |
| Sewer | 12/5/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/22/2025 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/30/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 1/31/2025 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 3/4/2025 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 3/4/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/29/2025 | Partial Approval | TEMISTOCLES CAAL |
| Green Building Rough | 4/29/2025 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 5/13/2025 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 5/13/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 5/13/2025 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 5/13/2025 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | KEVIN SARGSYAN |
| Insulation | 7/14/2025 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 7/24/2025 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/10/2025 | Approved | STEPHANIE SWANSON |
| Gas Test | 2/20/2026 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 3/2/2026 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 3/2/2026 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/4/2026 | Approved | EVAN COOPER |
| HVAC-Final | 3/24/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/24/2026 | Approved | EVAN COOPER |
| Final | 4/20/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| Green Building Final | 4/20/2026 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2026 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 4/20/2026 | Approved | KEVIN SARGSYAN |