8623 W AIRDROME ST 90035
Certificate Information: 8623 W AIRDROME ST 90035
- Application / Permit
- 23014-30000-00582
- Plan Check / Job No.
- B23WL00372
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2nd story addition and conversion of (e) det. garage to an ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/2/2023 | REZA HAGHIGHAT |
| Corrections Issued | 3/8/2023 | REZA HAGHIGHAT |
| Quality Review Completed | 3/14/2023 | KAVIAN REFAHI |
| Building Plans Picked Up | 3/15/2023 | APPLICANT |
| Plan Check Approved | 5/12/2023 | REZA HAGHIGHAT |
| Issued | 5/12/2023 | APPLICANT |
| CofO in Progress | 1/22/2026 | WILBER ROSALES |
| Permit Finaled | 2/3/2026 | RICHARD STEINBACH |
| CofO Issued | 2/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/10/2023 | WALTER RAMIREZ |
| Address approval | Cleared | 3/29/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2023 | TREVOR QUAN |
| Sewer availability | Cleared | 4/4/2023 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 4/15/2023 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 4/27/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 4/27/2023 | WALLIE JONG |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Barrier | 5/18/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Subgrade | 5/18/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Rough | 6/13/2023 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Subgrade | 6/13/2023 | Approved | JEREMY TODD |
| Sewer | 6/13/2023 | Approved | JEREMY TODD |
| METHANE-Barrier | 6/22/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 6/22/2023 | Partial Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2023 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 9/25/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 9/27/2023 | Not Ready for Inspection | BEN MOLSTAD |
| METHANE-Rough | 9/27/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Wood Frame | 9/27/2023 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 11/7/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Wood Frame | 11/7/2023 | Corrections Issued | MEL KHACHATOURIAN |
| Special/Order Compliance | 4/19/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 5/3/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Special/Order Compliance | 5/14/2024 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 1/16/2025 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 1/16/2025 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 1/16/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 1/16/2025 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 1/16/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/16/2025 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 3/4/2025 | Corrections Issued | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 3/4/2025 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/3/2025 | Approved | EVAN COOPER |
| Green Building Rough | 4/3/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 4/3/2025 | Partial Approval | EVAN COOPER |
| Insulation | 4/25/2025 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 5/22/2025 | Corrections Issued | ARAM AVEDISIAN |
| Drywall Nailing | 10/28/2025 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 10/28/2025 | Corrections Issued | EVAN COOPER |
| Final | 10/28/2025 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 10/28/2025 | Approved | EVAN COOPER |
| Gas Test | 10/28/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 10/28/2025 | Approved | EVAN COOPER |
| HVAC-Final | 10/28/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 10/28/2025 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/28/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 10/28/2025 | Approved | EVAN COOPER |
| Special/Order Compliance | 11/3/2025 | Not Ready for Inspection | EVAN COOPER |
| Drywall Nailing | 11/7/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/7/2025 | Approved | EVAN COOPER |
| Final | 11/7/2025 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 11/7/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 11/7/2025 | Approved | EVAN COOPER |
| Final | 1/21/2026 | OK to Issue CofO | WILBER ROSALES |