4481 E HUNTINGTON DR SOUTH 90032

Certificate Information: 4481 E HUNTINGTON DR SOUTH 90032

Application / Permit
23014-30000-00519
Plan Check / Job No.
B23WL00328
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ROOM ADDITION IN (E) SFD PER ENGINEER'S CALCS
Permit Issued
Issued on 3/20/2023
Issuing Office
West Los Angeles
Current Status
Issued on 3/20/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/8/2023 APPLICANT
Assigned to Plan Check Engineer 2/15/2023 RICHARD GARCIA
Corrections Issued 2/15/2023 RICHARD GARCIA
Building Plans Picked Up 2/17/2023 APPLICANT
Applicant returned to address corrections 3/7/2023 AMY GUEVARRA
Plan Check Approved 3/9/2023 DAVID CASTILLO
Issued 3/20/2023 APPLICANT

Permit Application Clearance Information

ZI Cleared 2/23/2023 DANIEL CORONADO
Grading Pre-Inspection Cleared 2/27/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 3/1/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/2/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Alferez,, Vicente Narvaez; Lic. No.: C53875 460 E CARSON PLAZA DR STE 212      CARSON, CA 90746

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/4/2023 Not Ready for Inspection AMY COLIN
Drywall Nailing 10/4/2023 Not Ready for Inspection AMY COLIN
Final 10/4/2023 Not Ready for Inspection AMY COLIN
Footing/Foundation/Slab 10/4/2023 Corrections Issued AMY COLIN
Green Building Final 10/4/2023 Not Ready for Inspection AMY COLIN
Green Building Rough 10/4/2023 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Not Ready AMY COLIN
Smoke Detectors 10/4/2023 Not Ready for Inspection AMY COLIN
BUILDING-Rough-Frame 10/16/2023 Corrections Issued AMY COLIN
Drywall Nailing 10/16/2023 Not Ready for Inspection AMY COLIN
Final 10/16/2023 Not Ready for Inspection AMY COLIN
Footing/Foundation/Slab 10/16/2023 Not Ready for Inspection AMY COLIN
Green Building Final 10/16/2023 Not Ready for Inspection AMY COLIN
Green Building Rough 10/16/2023 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready AMY COLIN
Smoke Detectors 10/16/2023 Not Ready for Inspection AMY COLIN
Footing/Foundation/Slab 10/20/2023 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 11/1/2023 Corrections Issued AMY COLIN
Excavation/Setback/Form/Re-Bar 11/3/2023 Corrections Issued AMY COLIN
ELECTRICAL-Rough 12/6/2023 Approved AMY COLIN
Rough-Elec/Plmb/HVAC 12/6/2023 Approved AMY COLIN
Wood Frame 12/6/2023 Approved AMY COLIN
Interior/Exterior Lathing 12/8/2023 Approved AMY COLIN