1466 N SAN REMO DR 90272
Certificate Information: 1466 N SAN REMO DR 90272
- Application / Permit
- 23014-30000-00350
- Plan Check / Job No.
- B23WL00207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to (E) Single Family Dwelling to create new master bathroom
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 5/10/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2023 | EDWIN ESPIN |
| Corrections Issued | 2/15/2023 | EDWIN ESPIN |
| Quality Review Completed | 2/21/2023 | JASON JANGADA |
| Building Plans Picked Up | 2/23/2023 | APPLICANT |
| Applicant returned to address corrections | 4/4/2023 | EDWIN ESPIN |
| Plan Check Approved | 5/8/2023 | EDWIN ESPIN |
| Issued | 5/10/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/4/2023 | EDWIN ESPIN |
| Roof/Waste drainage to street | Cleared | 4/8/2023 | KEVIN AVILA |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 4/10/2023 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 4/10/2023 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2023 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Miller Steven Louis; Lic. No.: 474691-B | 15021 VENTURA BLVD 702 SHERMAN OAKS, CA 91403 |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
| Geologist | Hill,, Thomas George; Lic. No.: EG1100 | 3210 VAL VERDE LONG BEACH, CA 90808 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/28/2023 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/28/2023 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 8/4/2023 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/7/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 8/8/2023 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/17/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 8/30/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/11/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 10/11/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 10/11/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 10/13/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 10/13/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 10/13/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/7/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/7/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/7/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 11/7/2023 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/9/2023 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 11/9/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/9/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/14/2023 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | No Access for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/14/2023 | No Access for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/27/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 11/27/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/27/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/29/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/29/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/29/2023 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/4/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 12/4/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 12/4/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 12/4/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/4/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/4/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 5/22/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/10/2024 | Approved | EVAN COOPER |