720 N ORANGE DR 90038

Certificate Information: 720 N ORANGE DR 90038

Application / Permit
23014-30000-00250
Plan Check / Job No.
B23WL00139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2nd story addition and partial conversion of existing garage at the rear of the lot to an ADU per LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 4/10/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2023 APPLICANT
Assigned to Plan Check Engineer 2/15/2023 AMY GUEVARRA
Corrections Issued 2/17/2023 AMY GUEVARRA
Quality Review Completed 2/21/2023 JASON JANGADA
Building Plans Picked Up 3/16/2023 APPLICANT
Applicant returned to address corrections 4/4/2023 AMY GUEVARRA
Plan Check Approved 4/10/2023 AMY GUEVARRA
Issued 4/10/2023 APPLICANT
CofO in Progress 3/27/2024 ROY SPAULDING
Permit Finaled 11/24/2024 DEROLD HAUFF
CofO Issued 11/24/2024 DEROLD HAUFF
Permit Finaled 11/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/3/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 4/3/2023 TREVOR QUAN
Sewer availability Cleared 4/3/2023 TREVOR QUAN
Construction within easement Cleared 4/5/2023 TINA MIRANDA
Roof/Waste drainage to street Cleared 4/5/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Kaligi,, Sean; Lic. No.: M37797 655 N CENTRAL AVE 17TH FL      GLENDALE, CA 91203

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2023 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 5/23/2023 Corrections Issued JOAQUIN GREENOUGH
Underground Mechanical 5/23/2023 Corrections Issued JOAQUIN GREENOUGH
METHANE-Subgrade 5/26/2023 Approved BRIAN SULLIVAN
Underground Mechanical 5/26/2023 Partial Approval BRIAN SULLIVAN
METHANE-Barrier 5/30/2023 Approved BRIAN SULLIVAN
Underground Mechanical 5/30/2023 Not Ready for Inspection BRIAN SULLIVAN
Deputy Reinf. Concrete 6/2/2023 Partial Approval RUBEN SALAS
Excavation/Setback/Form/Re-Bar 6/2/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/7/2023 Conditional Approval JOAQUIN GREENOUGH
Deputy Reinf. Concrete 6/8/2023 Partial Approval RUBEN SALAS
Underground Mechanical 6/16/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/20/2023 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 9/20/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Partial Approval JOAQUIN GREENOUGH
Green Building Rough 9/20/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 9/20/2023 Corrections Issued JOAQUIN GREENOUGH
METHANE-Rough 9/20/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 9/20/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 9/29/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/29/2023 Partial Approval BRIAN SULLIVAN
METHANE-Rough 9/29/2023 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 10/4/2023 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Not Ready for Inspection BRIAN SULLIVAN
Green Building Rough 10/4/2023 Approved BRIAN SULLIVAN
HVAC-Rough 10/4/2023 Approved BRIAN SULLIVAN
Shower Pan 10/4/2023 Approved BRIAN SULLIVAN
Wood Frame 10/4/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 10/18/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2023 Approved STUART CHAPMAN
Wood Frame 10/18/2023 Approved STUART CHAPMAN
Insulation 11/1/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/1/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 11/7/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/7/2023 Approved JOAQUIN GREENOUGH
Underground Mechanical 1/17/2024 Approved BRIAN SULLIVAN
Service/Power Release 1/23/2024 Approved DAVID FEILER
ELECTRICAL-Final 2/2/2024 Not Ready for Inspection ROY SPAULDING
Final 2/2/2024 Not Ready for Inspection ROY SPAULDING
Footing/Foundation/Slab 2/2/2024 Approved ROY SPAULDING
Green Building Final 2/2/2024 Not Ready for Inspection ROY SPAULDING
HVAC-Final 2/2/2024 Not Ready for Inspection ROY SPAULDING
PLUMBING-Final 2/2/2024 Not Ready for Inspection ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 2/2/2024 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Final 2/7/2024 Approved BRIAN SULLIVAN
Final 2/7/2024 Corrections Issued BRIAN SULLIVAN
Green Building Final 2/7/2024 Approved BRIAN SULLIVAN
HVAC-Final 2/7/2024 Approved BRIAN SULLIVAN
PLUMBING-Final 2/7/2024 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 2/7/2024 Approved BRIAN SULLIVAN
Final 3/11/2024 Corrections Issued ROY SPAULDING
Final 3/26/2024 OK to Issue CofO ROY SPAULDING