2152 S PARNELL AVE 90025
Certificate Information: 2152 S PARNELL AVE 90025
- Application / Permit
- 23014-30000-00157
- Plan Check / Job No.
- B23WL00099
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 387 sf Single story addition and remodel to (e) S.F.D. per engineer's calcs.
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | RICHARD GARCIA |
| Corrections Issued | 1/20/2023 | RICHARD GARCIA |
| Building Plans Picked Up | 1/23/2023 | APPLICANT |
| Plan Check Approved | 1/27/2023 | ALFREDO JARA |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 12/21/2023 | ROBERT CHAVEZ |
| Permit Finaled | 1/11/2024 | DANIEL SANCHEZ |
| CofO Issued | 1/11/2024 | DANIEL SANCHEZ |
| Permit Finaled | 1/11/2024 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 1/24/2023 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 1/24/2023 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 1/24/2023 | ASHLEY RODARTE |
| ZI | Cleared | 1/24/2023 | ASHLEY RODARTE |
| Grading Pre-Inspection | Cleared | 1/25/2023 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PETER RUBIO, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN TCHANG, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| RYAN TAGUINES, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/2/2023 | Partial Approval | JOHN TCHANG |
| METHANE-Barrier | 2/2/2023 | Approved | JOHN TCHANG |
| METHANE-Subgrade | 2/2/2023 | Approved | JOHN TCHANG |
| Deputy Drilled-In Anchors | 2/3/2023 | Conditional Approval | ROBERT CHAVEZ |
| BUILDING-Rough-Frame | 2/7/2023 | Partial Approval | JOHN TCHANG |
| Footing/Foundation/Slab | 2/7/2023 | Corrections Issued | JOHN TCHANG |
| Green Building Rough | 2/7/2023 | Approved | JOHN TCHANG |
| METHANE-Rough | 2/7/2023 | Approved | JOHN TCHANG |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Partial Approval | ROBERT CHAVEZ |
| Footing/Foundation/Slab | 2/16/2023 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Rough | 3/22/2023 | Approved | ROBERT CHAVEZ |
| PLUMBING-Rough | 3/22/2023 | Approved | ROBERT CHAVEZ |
| Wood Frame | 3/22/2023 | Partial Approval | ROBERT CHAVEZ |
| Drywall Nailing | 3/30/2023 | Approved | ROBERT CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Approved | ROBERT CHAVEZ |
| Interior/Exterior Lathing | 4/5/2023 | Approved | PETER RUBIO |
| Shower Pan | 4/5/2023 | Approved | PETER RUBIO |
| BUILDING-Rough-Frame | 8/4/2023 | Approved | ROBERT CHAVEZ |
| Final | 8/4/2023 | Conditional Approval | ROBERT CHAVEZ |
| Green Building Final | 8/4/2023 | Approved | ROBERT CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 8/4/2023 | SGSOV Approved | ROBERT CHAVEZ |
| Smoke Detectors | 8/4/2023 | Approved | ROBERT CHAVEZ |
| Final | 12/21/2023 | OK to Issue CofO | ROBERT CHAVEZ |