6028 N ST CLAIR AVE 91606

Certificate Information: 6028 N ST CLAIR AVE 91606

Application / Permit
23014-20001-05143
Plan Check / Job No.
B24VN04408
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 23014-20000-05143 TO REVISE WORK DESCRIPTION TO: "(N) ADDITION 36'-7" X 35'-9" ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT" NO CHANGE IN HEIGHT
Permit Issued
Issued on 4/3/2024
Issuing Office
Valley
Current Status
Permit Finaled on 1/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/3/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/3/2024 SEWADA ZADOORAN MILAGARDI
Issued 4/3/2024 APPLICANT
Permit Finaled 1/17/2025 OGANES TARAKHCHYAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/20/2024 Partial Approval JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/28/2024 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 7/2/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/19/2024 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval JACK KARGODORIAN
Green Building Rough 8/19/2024 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Rough 8/19/2024 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 8/19/2024 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 8/21/2024 Approved SALVADOR MARTINEZ
HVAC-Rough 8/21/2024 Approved SALVADOR MARTINEZ
Special/Order Compliance 8/21/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/26/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/29/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/6/2024 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/6/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 9/6/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/23/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 9/23/2024 Approved OGANES TARAKHCHYAN
MERV13>=Rough 9/23/2024 Approved OGANES TARAKHCHYAN
Insulation 9/27/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 10/4/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/4/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Final 12/20/2024 Approved OGANES TARAKHCHYAN
Pre-Inspection 12/20/2024 Corrections Issued OGANES TARAKHCHYAN
Service/Power Release 12/20/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/27/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 12/27/2024 Approved OGANES TARAKHCHYAN
Final 1/17/2025 Permit Finaled OGANES TARAKHCHYAN
Green Building Final 1/17/2025 Approved OGANES TARAKHCHYAN
MERV13>=Final 1/17/2025 Approved OGANES TARAKHCHYAN