261 W 43RD PL 90037
Certificate Information: 261 W 43RD PL 90037
- Application / Permit
- 23014-20001-02507
- Plan Check / Job No.
- B23VN13825
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental to update plans to meet existing site conditions as well as change the previous design of a laundry to a bathroom and change the entry to one of the bedrooms and exterior rear exit and make a stackable laundry unit beside the new bathrooms.
- Permit Issued
- Issued on 10/26/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2023 | JOE VO |
| Plan Check Approved | 10/23/2023 | JOE VO |
| Issued | 10/26/2023 | APPLICANT |
| Permit Finaled | 8/15/2024 | BRENDAN MORELLI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Roof Replacement Inc; Lic. No.: 1063655-B | , |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 6/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Final | 6/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| MERV13>=Rough | 6/6/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/6/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/17/2024 | No Access for Inspection | DAVID FEILER |
| Final | 6/17/2024 | No Access for Inspection | DAVID FEILER |
| Green Building Final | 6/17/2024 | No Access for Inspection | DAVID FEILER |
| HVAC-Final | 6/17/2024 | No Access for Inspection | DAVID FEILER |
| PLUMBING-Final | 6/17/2024 | No Access for Inspection | DAVID FEILER |
| Smoke Detectors | 6/17/2024 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 6/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 6/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/25/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 8/9/2024 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 8/9/2024 | Partial Inspection | MICHAEL LEWIS |
| Final | 8/15/2024 | Permit Finaled | BRENDAN MORELLI |
| Green Building Final | 8/15/2024 | Approved | BRENDAN MORELLI |