19803 W ROSCOE BLVD 91306

Certificate Information: 19803 W ROSCOE BLVD 91306

Application / Permit
23014-20000-05396
Plan Check / Job No.
B23VN17914
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN Add (E) enclosed covered patio with new addition to (E) 1-story SFD and remodel. Per WFPP. See comments
Permit Issued
Issued on 5/2/2024
Issuing Office
Current Status
CofO Issued on 2/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2024 APPLICANT
Assigned to Plan Check Engineer 1/5/2024 MINA HABILI
Corrections Issued 1/6/2024 MINA HABILI
Applicant returned to address corrections 2/1/2024 NEHEMIAS RAMOS
Plan Check Approved 4/19/2024 DANIEL SANJUAN
Issued 5/2/2024 APPLICANT
CofO in Progress 2/12/2025 CHRIS CHRISTENSEN
Permit Finaled 2/24/2025 JOHN JANSON
CofO Issued 2/24/2025 JOHN JANSON
Permit Finaled 2/24/2025 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 1/16/2024 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 3/5/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 3/5/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 3/5/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval CHRIS CHRISTENSEN
Insulation 11/6/2024 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 11/20/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 11/20/2024 Approved CHRIS CHRISTENSEN
Wood Frame 11/20/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/27/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 11/27/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/27/2024 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 12/2/2024 Approved TROY SANDERS
Insulation 12/2/2024 Approved TROY SANDERS
Final 2/6/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 2/6/2025 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 2/6/2025 Approved CHRIS CHRISTENSEN
Final 2/11/2025 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 2/11/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved CHRIS CHRISTENSEN