12569 N TELFAIR AVE 91342

Certificate Information: 12569 N TELFAIR AVE 91342

Application / Permit
23014-20000-05379
Plan Check / Job No.
B23VN17883
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) SFD, ADD 24'-0" X 17'-0" (IRREGULAR SHAPED) , 10'-0" X 21'-0" & 7'-0" X 10'-0" PORCH PER WFPP. NFPA 13D FIRE SPRINKLER REQUIRED THROUGHOUT.
Permit Issued
Issued on 5/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2023 APPLICANT
Assigned to Plan Check Engineer 1/6/2024 ARTIN ZARUKIAN
Corrections Issued 1/6/2024 ARTIN ZARUKIAN
Building Plans Picked Up 1/9/2024 APPLICANT
Issued 5/2/2024 APPLICANT
CofO in Progress 11/13/2025 KEVIN BERBERYAN
Permit Finaled 11/21/2025 RUBEN SALAS
CofO Issued 11/21/2025 RUBEN SALAS
Permit Finaled 11/21/2025 RUBEN SALAS

Permit Application Clearance Information

Tenant Habitability Plan Cleared 1/22/2024 RICARDO BOHORQUEZ
ZA Case Cleared 1/22/2024 ASHLEY RODARTE
Miscellaneous Cleared 1/23/2024 STEVEN WECHSLER
Grading Pre-Inspection Cleared 2/2/2024 CHARLES POWELL
Low Impact Development (LID) Cleared 3/8/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/24/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/26/2024 CARLOS AGUILERA
Sewer availability Cleared 4/26/2024 CARLOS AGUILERA
GPI Written Notices Cleared 5/2/2024 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/6/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 5/7/2024 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval JOHN COLEMAN
Deputy Drilled-In Anchors 6/21/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/21/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/4/2024 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 10/4/2024 Corrections Issued KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Partial Approval KEVIN BERBERYAN
Green Building Rough 10/4/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 10/4/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 10/4/2024 Conditional Approval KEVIN BERBERYAN
Interior/Exterior Lathing 10/31/2024 Approved LOUIS ESCOTO
Shower Pan 10/31/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 11/19/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 11/19/2024 Approved KEVIN BERBERYAN
Green Building Rough 11/19/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/19/2024 Approved KEVIN BERBERYAN
Insulation 11/26/2024 Approved KEVIN BERBERYAN
Drywall Nailing 12/6/2024 Approved MICHAEL CORTEZ
Sewer 9/17/2025 Approved KEVIN BERBERYAN
Final 10/24/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 10/24/2025 Approved KEVIN BERBERYAN
Green Building Final 10/24/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 10/24/2025 Approved KEVIN BERBERYAN
Final 11/3/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 11/3/2025 Approved KEVIN BERBERYAN
Service/Power Release 11/3/2025 Approved KEVIN BERBERYAN