4911 N LEMONA AVE 91403
Certificate Information: 4911 N LEMONA AVE 91403
- Application / Permit
- 23014-20000-05357
- Plan Check / Job No.
- B23VN17831
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 355 SF ADDITION TO AND CONVERT (E) 369 SF DETACHED GARAGE TO (N) 724 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 1/9/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/10/2024 | APPLICANT |
| Plan Check Approved | 6/3/2024 | LUISANGEL VALENZUELA |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | JACK KARGODORIAN |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
| CofO Issued | 6/12/2025 | RUBEN SALAS |
| Permit Finaled | 6/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/11/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/19/2024 | EDGAR ALCARAZ |
| ZI | Cleared | 3/6/2024 | BRENNEN OBETO |
| Construction near power lines | Cleared | 5/23/2024 | TINA MIRANDA |
Contact Information
| Contractor | Builders Boulevard Inc; Lic. No.: 1052531-B | 6320 TOPANGA CANYON BLVD 1630 WOODLAND HILLS, CA 91367 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/27/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/28/2024 | Approved | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Corrections Issued | JACK KARGODORIAN |
| Sewer | 8/30/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 9/3/2024 | Approved | JACK KARGODORIAN |
| Sewer | 9/20/2024 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 9/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 9/25/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/2/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 10/2/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 10/8/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/10/2024 | Corrections Issued | DAVID MATSON |
| HVAC-Rough | 10/10/2024 | Corrections Issued | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/22/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/22/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 10/22/2024 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 10/22/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 10/22/2024 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/23/2024 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/28/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Shower Pan | 10/28/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/29/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 10/30/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 11/8/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 11/8/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/15/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 11/15/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/25/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 3/25/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 3/25/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/25/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 3/25/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 3/25/2025 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 3/25/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 3/25/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 3/25/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/16/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/16/2025 | Approved | JENNIFER RABUCHIN |