11343 W CALVERT ST 91606
Certificate Information: 11343 W CALVERT ST 91606
- Application / Permit
- 23014-20000-05344
- Plan Check / Job No.
- B23VN17788
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE (333 SF) AND (N) 7'-9" X 15'-1" ADDITION (116 SF) TO (N) ACCESSORY DWELLING UNIT (449 SF) PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER WFPP DESIGN.
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | ISIS ARGUETA |
| Corrections Issued | 1/4/2024 | ISIS ARGUETA |
| Building Plans Picked Up | 1/5/2024 | APPLICANT |
| Applicant returned to address corrections | 1/22/2024 | MADISON ODELL |
| Plan Check Approved | 6/6/2024 | ALEC MOUSAKHANIAN |
| Issued | 6/6/2024 | APPLICANT |
| CofO in Progress | 5/30/2025 | JOSE AVILA |
| CofO Issued | 7/16/2025 | RUBEN SALAS |
| Permit Finaled | 7/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2024 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 2/6/2024 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2024 | RYAN KIM |
| Sewer availability | Cleared | 2/13/2024 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 6/28/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 7/1/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 7/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/31/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 9/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/6/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/12/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 12/4/2024 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 12/10/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 12/13/2024 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 12/24/2024 | Partial Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 12/30/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 12/30/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 12/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 1/6/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 1/10/2025 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 1/10/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/13/2025 | Approved | JOSE AVILA |
| Green Building Rough | 1/13/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 1/13/2025 | Approved | JOSE AVILA |
| Insulation | 1/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 1/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 1/24/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/26/2025 | Corrections Issued | JOSE AVILA |
| Final | 3/18/2025 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 4/14/2025 | Approved | JOSE AVILA |
| Green Building Final | 4/23/2025 | Approved | JOSE AVILA |
| HVAC-Final | 4/23/2025 | Approved | JOSE AVILA |
| Underground Mechanical | 4/28/2025 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 5/1/2025 | Not Ready for Inspection | JOSE AVILA |
| Final | 5/8/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/8/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Final | 5/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/20/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/27/2025 | OK to Issue CofO | JOSE AVILA |