6825-6827 N RANCHITO AVE 91405

Certificate Information: 6825-6827 N RANCHITO AVE 91405

Application / Permit
23014-20000-05336
Plan Check / Job No.
B23VN17744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Addition and Major Remodel of existing 1-story Single Family Dwelling, only 10 linear feet of exterior wall on East portion of Lot to remain and all existing foundation to remain . Rebuilt as 1-story ( 81' 6" x 40') Duplex per SB9. NFPA 13D Fire Sprinklers. All work done per engineer.
Permit Issued
Issued on 3/13/2024
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2023 APPLICANT
Assigned to Plan Check Engineer 1/19/2024 NAREG ATARIAN
Corrections Issued 1/20/2024 NAREG ATARIAN
Quality Review Completed 1/24/2024 OMID HEDAYAT
Applicant returned to address corrections 3/11/2024 NAREG ATARIAN
Plan Check Approved 3/13/2024 NAREG ATARIAN
Issued 3/13/2024 APPLICANT
CofO in Progress 4/29/2025 RYAN SALAZAR
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/23/2024 COLIN LOREDO
Low Impact Development (LID) Cleared 1/23/2024 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 1/24/2024 COLIN LOREDO
Roof/Waste drainage to street Cleared 1/24/2024 COLIN LOREDO
Sewer availability Cleared 1/24/2024 COLIN LOREDO
Senate Bill 9 Cleared 2/20/2024 ALEX VELA
Hydrant and Access approval Cleared 3/7/2024 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/24/2024 Not Ready for Inspection JOHN COLEMAN
Underground Mechanical 4/24/2024 Corrections Issued JOHN COLEMAN
Deputy Drilled-In Anchors 5/9/2024 Conditional Approval MATTHEW NELSON
PLUMBING-Rough 5/28/2024 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 6/3/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/4/2024 Corrections Issued JOHN COLEMAN
HVAC-Rough 6/4/2024 Corrections Issued JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 6/6/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 8/16/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved RYAN SALAZAR
HVAC-Rough 8/16/2024 Approved RYAN SALAZAR
PLUMBING-Rough 8/16/2024 Partial Approval RYAN SALAZAR
Rough-Elec/Plmb/HVAC 8/16/2024 Conditional Approval RYAN SALAZAR
BUILDING-Rough-Frame 8/26/2024 Approved RYAN SALAZAR
Green Building Rough 8/26/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/26/2024 Not Ready for Inspection RYAN SALAZAR
Rough-Elec/Plmb/HVAC 8/26/2024 Approved RYAN SALAZAR
Underground Mechanical 9/25/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/2/2024 Partial Approval RYAN SALAZAR
Insulation 10/9/2024 Approved RYAN SALAZAR
Drywall Nailing 10/16/2024 Approved RYAN SALAZAR
Shower Pan 11/4/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/7/2024 Approved RYAN SALAZAR
Final 3/6/2025 Corrections Issued RYAN SALAZAR
Footing/Foundation/Slab 3/6/2025 Approved RYAN SALAZAR
Green Building Final 3/6/2025 Not Ready for Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 3/6/2025 Approved RYAN SALAZAR
Final 4/16/2025 Partial Approval RYAN SALAZAR
Green Building Final 4/16/2025 Approved RYAN SALAZAR
Final 4/30/2025 OK to Issue CofO RYAN SALAZAR