12200 W CALIFA ST 91607
Certificate Information: 12200 W CALIFA ST 91607
- Application / Permit
- 23014-20000-05309
- Plan Check / Job No.
- B23VN17665
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ENTIRE SFD W/ ATTACHED GARAGE EXCEPT 1LF WALL & FOOTING & ADD 1-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 3/12/2024
- Issuing Office
- Current Status
- CofO Issued on 2/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2024 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/7/2024 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/11/2024 | JASON HEALEY |
| Applicant returned to address corrections | 2/28/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/11/2024 | NILOOFAR MEHRAIN |
| Issued | 3/12/2024 | APPLICANT |
| CofO in Progress | 1/14/2026 | WAYNE REGESTER |
| Permit Finaled | 2/18/2026 | RUBEN SALAS |
| CofO Issued | 2/18/2026 | RUBEN SALAS |
| Permit Finaled | 2/18/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 2/16/2024 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 2/16/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | L S Assessment Inc; Lic. No.: 1056351-B | , |
| Contractor | L S Remodeling; Lic. No.: 1056351-B | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/28/2024 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/28/2024 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/3/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/11/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 10/1/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/1/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/16/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/16/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/23/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/28/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/28/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 2/6/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 2/6/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/18/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/3/2025 | Approved | MICHAEL CORTEZ |
| Insulation | 3/10/2025 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 3/19/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/26/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/1/2025 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/17/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Final | 11/24/2025 | Approved | WAYNE REGESTER |
| Gas Test | 12/2/2025 | Not Ready for Inspection | WAYNE REGESTER |
| PLUMBING-Final | 12/2/2025 | Partial Approval | WAYNE REGESTER |
| Drywall Nailing | 12/9/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Final | 12/9/2025 | Approved | WAYNE REGESTER |
| ELECTRICAL-Rough | 12/9/2025 | Approved | WAYNE REGESTER |
| Excavation/Setback/Form/Re-Bar | 12/9/2025 | Approved | WAYNE REGESTER |
| Final | 12/9/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Approved | WAYNE REGESTER |
| Footing/Foundation/Slab | 12/9/2025 | Approved | WAYNE REGESTER |
| Gas Test | 12/9/2025 | Approved | WAYNE REGESTER |
| HVAC-Final | 12/9/2025 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Rough | 12/9/2025 | Approved | WAYNE REGESTER |
| Insulation | 12/9/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 12/9/2025 | Approved | WAYNE REGESTER |
| Masonry Wall/Backfill | 12/9/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 12/9/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 12/9/2025 | Approved | WAYNE REGESTER |
| Pre-Inspection | 12/9/2025 | Approved | WAYNE REGESTER |
| Rough-Elec/Plmb/HVAC | 12/9/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 12/9/2025 | SGSOV Approved | WAYNE REGESTER |
| Sewer | 12/9/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 12/9/2025 | Approved | WAYNE REGESTER |
| Wood Frame | 12/9/2025 | Approved | WAYNE REGESTER |
| Final | 12/29/2025 | Conditional Approval | WAYNE REGESTER |
| Final | 1/6/2026 | Not Ready for Inspection | WAYNE REGESTER |
| HVAC-Final | 1/6/2026 | Approved | WAYNE REGESTER |
| Final | 1/14/2026 | OK to Issue CofO | WAYNE REGESTER |
| Special/Order Compliance | 1/21/2026 | Corrections Issued | JOAQUIN GREENOUGH |