15454 W LULL ST 91406
Certificate Information: 15454 W LULL ST 91406
- Application / Permit
- 23014-20000-05271
- Plan Check / Job No.
- B23VN17574
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ****ePlan**** 2-story addition to (e) det. garage and conversion to an ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2024 | REZA HAGHIGHAT |
| Corrections Issued | 2/13/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 2/20/2024 | KAVIAN REFAHI |
| Plan Check Approved | 8/25/2024 | REZA HAGHIGHAT |
| Issued | 8/29/2024 | APPLICANT |
| CofO in Progress | 4/6/2025 | VINCENT HANLEY |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| CofO Issued | 4/15/2025 | RUBEN SALAS |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 8/8/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 8/14/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/19/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 9/23/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 9/25/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/25/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Wood Construction | 10/23/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/13/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 11/13/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 11/13/2024 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 11/13/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 11/13/2024 | Approved | VINCENT HANLEY |
| Insulation | 11/26/2024 | Corrections Issued | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/26/2024 | Partial Approval | VINCENT HANLEY |
| Drywall Nailing | 12/6/2024 | Approved | RYAN SALAZAR |
| Sewer | 1/27/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 1/27/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/4/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 3/4/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 3/4/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 3/4/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/4/2025 | Approved | VINCENT HANLEY |
| Final | 4/4/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 4/4/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/4/2025 | Approved | VINCENT HANLEY |