8823 N ENCINO AVE 91325
Certificate Information: 8823 N ENCINO AVE 91325
- Application / Permit
- 23014-20000-05263
- Plan Check / Job No.
- B23VN17559
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE 1'-10" X 21'-4" PORTION OF SFD. IRREG SHAPED ADDITIONS AND MAJOR REMODEL TO (E) SFD. REFRAME ENTIRE ROOF. ADD COVERED PORCH. (NFPA 13D FIRE SPRINKLERS REQUIRED)
- Permit Issued
- Issued on 4/3/2025
- Issuing Office
- Valley
- Current Status
- Issued on 4/3/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 12/30/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/3/2024 | APPLICANT |
| Plan Check Approved | 6/28/2024 | DANIEL ABRAMYAN |
| Issued | 4/3/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/16/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 4/22/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/25/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | True Enterprises Inc; Lic. No.: 655129-B | 8823 ENCINO AVE NORTHRIDGE, CA 91325 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/23/2025 | Conditional Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 6/24/2025 | Conditional Approval | RAUL OLAGI |
| Underground Mechanical | 6/24/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 7/2/2025 | Approved | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 7/16/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Underground Mechanical | 7/18/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Wood Frame | 7/18/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Approved | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 9/8/2025 | Approved | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 2/13/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/13/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/13/2026 | Approved | CHRISTOPHER ROJAS |
| Special/Order Compliance | 2/13/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 2/27/2026 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/26/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/26/2026 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 3/26/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 3/26/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 4/10/2026 | Approved | CHRISTOPHER ROJAS |
| Insulation | 4/10/2026 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 4/10/2026 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 4/23/2026 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/23/2026 | Approved | CHRISTOPHER ROJAS |