2511 N COMMONWEALTH AVE 90027
Certificate Information: 2511 N COMMONWEALTH AVE 90027
- Application / Permit
- 23014-20000-05249
- Plan Check / Job No.
- B23VN17524
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO EXISTING SINGLE FAMILY DWELLING WITH NEW 9'-5" X 14'-6" ADDITION TO ENLARGE EXISTING BEDROOM AND NEW 5'-9" X 14'-6" ADDITION TO CREATE NEW COVER PATIO
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | JESSE ARELLANO |
| Corrections Issued | 1/3/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 1/10/2024 | APPLICANT |
| Plan Check Approved | 3/5/2024 | ALEC MOUSAKHANIAN |
| Issued | 6/6/2024 | APPLICANT |
| CofO in Progress | 5/1/2025 | ENRIQUE MIRELES |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/13/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 1/13/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 3/5/2024 | ALEC MOUSAKHANIAN |
Contact Information
| Architect | Eng,, Timothy J Y; Lic. No.: C35861 | 16718 BOLLINGER DRIVE PACIFIC PALISADES, CA 90272 |
| Contractor | Bello Building And Contracting Inc; Lic. No.: 998659-B | 3221 CARTER AVE #356 MARINA DEL REY, CA 90292 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/13/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/17/2024 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 9/17/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/17/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/30/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/30/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 10/30/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/30/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/20/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 11/22/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/27/2024 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 11/27/2024 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 12/6/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/26/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 4/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 4/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 4/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 4/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 4/14/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/15/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/15/2025 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 4/15/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/15/2025 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 4/15/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/23/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/23/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 4/23/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/23/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 4/23/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/25/2025 | Approved | ENRIQUE MIRELES |
| Final | 4/25/2025 | OK to Issue CofO | ENRIQUE MIRELES |
| PLUMBING-Final | 4/25/2025 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 4/25/2025 | Approved | ENRIQUE MIRELES |