20360 W KESWICK ST 91306
Certificate Information: 20360 W KESWICK ST 91306
- Application / Permit
- 23014-20000-05245
- Plan Check / Job No.
- B23VN17515
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- MAJOR REMODEL TO (E) DETACHED GARAGE TO KEEP ONE WALL AND TO CONVERT A PORTION WITH ADDITION INTO A (N) IRREGULAR SHAPED DETACHED 35'-4" x 46'-5"ACCESSORY DWELLING UNIT WITH AN ATTACHED 21'-0" x 21'-10" GARAGE TO COMPLY WITH LAMC 12.22 A.33(c) AND (d) PER ENGINEERING
- Permit Issued
- Issued on 1/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 3/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2023 | JESSE ARELLANO |
| Corrections Issued | 12/27/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 12/29/2023 | APPLICANT |
| Issued | 1/19/2024 | APPLICANT |
| CofO in Progress | 1/7/2025 | ALEXANDER HANDY |
| CofO Issued-Status Void | 1/23/2025 | JOHN JANSON |
| Permit Finaled-Status Void | 1/23/2025 | JOHN JANSON |
| Re-Activate Permit | 3/17/2025 | JOHN JANSON |
| CofO Corrected | 3/17/2025 | JOHN JANSON |
| Permit Finaled | 3/17/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2024 | EDGAR ALCARAZ |
| Low Impact Development (LID) | Cleared | 1/18/2024 | PATRICK LOPEZ |
| Roof/Waste drainage to street | Cleared | 1/18/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 1/19/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/19/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 4/19/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/19/2024 | Partial Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Approved | ARUTYUN MADATYAN |
| Deputy Wood Construction | 5/31/2024 | Conditional Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/2/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 7/2/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/2/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Rough-Elec/Plmb/HVAC | 7/2/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 7/5/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/5/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 7/10/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 8/2/2024 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 8/26/2024 | Approved | ARUTYUN MADATYAN |
| Underground Mechanical | 8/26/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 10/15/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Final | 10/15/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 10/15/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 10/15/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 10/15/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 10/15/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Smoke Detectors | 10/15/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 10/22/2024 | Approved | ARUTYUN MADATYAN |
| Final | 10/22/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 10/22/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 10/22/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 10/22/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 10/22/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 10/22/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 1/7/2025 | Approved | ALEXANDER HANDY |
| Final | 1/7/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 1/7/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 1/7/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/7/2025 | Approved | ALEXANDER HANDY |