9403-9405 N WYSTONE AVE 91324

Certificate Information: 9403-9405 N WYSTONE AVE 91324

Application / Permit
23014-20000-05244
Plan Check / Job No.
B23VN17512
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT AND RECONSTRUCT OF EXISTING DWELLING TO ADU AND NEW REAR COVERED PATIO ADDITION PER LAMC 12.22 A.33(c) and (e).
Permit Issued
Issued on 7/12/2024
Issuing Office
Current Status
CofO Issued on 11/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2023 APPLICANT
Assigned to Plan Check Engineer 1/3/2024 SHANGQIN XIE
Corrections Issued 1/4/2024 SHANGQIN XIE
Plan Check Approved 7/10/2024 TSE MING HUANG
Issued 7/12/2024 APPLICANT
CofO in Progress 10/27/2025 KRISTEN CAUSEY
Permit Finaled 11/7/2025 JOHN JANSON
CofO Issued 11/7/2025 JOHN JANSON
Permit Finaled 11/7/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/1/2024 COLIN LOREDO
Roof/Waste drainage to street Cleared 2/1/2024 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 2/5/2024 COLIN LOREDO
Sewer availability Cleared 2/5/2024 COLIN LOREDO
Construction near power lines Cleared 6/10/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: NA69935       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/21/2025 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Partial Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 4/2/2025 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 4/7/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 4/7/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 4/7/2025 Partial Approval DAVID SCANTLIN
Shower Pan 4/7/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 4/9/2025 Approved KRISTEN CAUSEY
Green Building Rough 4/9/2025 Approved KRISTEN CAUSEY
Insulation 4/9/2025 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 4/9/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 4/9/2025 Approved KRISTEN CAUSEY
Insulation 4/10/2025 Approved DAVID SCANTLIN
PLUMBING-Rough 4/10/2025 Approved DAVID SCANTLIN
Wood Frame 4/10/2025 Approved DAVID SCANTLIN
Drywall Nailing 4/16/2025 Approved KRISTEN CAUSEY
Drywall Nailing 4/21/2025 Approved TROY SANDERS
Final 7/3/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 7/14/2025 Corrections Issued DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 7/14/2025 Approved DAVID SCANTLIN
Final 9/17/2025 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Final 10/20/2025 Partial Inspection KRISTEN CAUSEY
Final 10/24/2025 OK to Issue CofO KRISTEN CAUSEY