7828 S KENYON AVE 90045
Certificate Information: 7828 S KENYON AVE 90045
- Application / Permit
- 23014-20000-05230
- Plan Check / Job No.
- B23VN17481
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED 18'4"X23'11" GARAGE INTO ACCESSORY DWELLING UNIT WITH 17'8"X15'9" ADDN PER LAMC 12.22A.33(c) & (d).
- Permit Issued
- Issued on 5/28/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | SERGIO MUNIZ |
| Corrections Issued | 12/23/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/4/2024 | APPLICANT |
| Issued | 5/28/2024 | APPLICANT |
| CofO in Progress | 12/21/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
| CofO Issued | 12/31/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/31/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 1/5/2024 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2024 | ANDREA SAINT-ANTONIN |
| Sewer availability | Cleared | 2/21/2024 | ANDREA SAINT-ANTONIN |
| Specific Plan | Cleared | 2/27/2024 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 2/28/2024 | VASIL MIHALEV |
| Construction near power lines | Cleared | 5/20/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Soul Builders Inc; Lic. No.: 1103425-B | 8517 VALLEY FLORES DR WEST HILLS, CA 91304 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JESUS PINEDA, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/28/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 6/28/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 7/3/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/26/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/28/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 9/23/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/23/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 9/24/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 10/2/2024 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 10/2/2024 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 10/2/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/4/2024 | Approved | BOBBY KEY |
| Green Building Rough | 10/4/2024 | Approved | BOBBY KEY |
| Insulation | 10/4/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 10/9/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 10/9/2024 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 10/11/2024 | Approved | MICHAEL ALLEN |
| Shower Pan | 10/11/2024 | Partial Approval | MICHAEL ALLEN |
| Shower Pan | 10/16/2024 | Corrections Issued | BOBBY KEY |
| Shower Pan | 10/18/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 12/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 12/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 12/10/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 12/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 12/10/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Smoke Detectors | 12/10/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/20/2024 | Approved | TEMISTOCLES CAAL |
| Final | 12/20/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 12/20/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 12/20/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | TEMISTOCLES CAAL |