3677 W EDENHURST AVE 90039

Certificate Information: 3677 W EDENHURST AVE 90039

Application / Permit
23014-20000-05221
Plan Check / Job No.
B23VN17471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel and Addition (26'-3" x 18' Irregular Shape) to North of existing 1-story Single Family Dwelling
Permit Issued
Issued on 2/14/2024
Issuing Office
Current Status
CofO Issued on 11/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 VAHAN JIVALAGIAN
Corrections Issued 1/16/2024 VAHAN JIVALAGIAN
Quality Review Completed 1/19/2024 OMID HEDAYAT
Building Plans Picked Up 1/24/2024 APPLICANT
Applicant returned to address corrections 2/12/2024 VAHAN JIVALAGIAN
Plan Check Approved 2/14/2024 VAHAN JIVALAGIAN
Issued 2/14/2024 APPLICANT
CofO in Progress 11/26/2024 THOMAS LOGRASSO
Permit Finaled 11/30/2024 DEROLD HAUFF
CofO Issued 11/30/2024 DEROLD HAUFF
Permit Finaled 11/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/27/2024 AMBER CAMPBELL
Sewer availability Cleared 1/27/2024 AMBER CAMPBELL
ZI Cleared 1/31/2024 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 2/13/2024 AMBER CAMPBELL

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/27/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/1/2024 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/2/2024 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 4/4/2024 Partial Approval HAMIK HARTOUNIAN
Insulation 4/10/2024 Partial Approval CHARLES BOGHOSKHAN
Wood Frame 4/10/2024 Partial Approval CHARLES BOGHOSKHAN
ELECTRICAL-Rough 5/28/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 5/28/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 5/28/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 6/4/2024 Corrections Issued THOMAS LOGRASSO
Sewer 6/4/2024 Approved THOMAS LOGRASSO
Green Building Rough 7/9/2024 Approved THOMAS LOGRASSO
Insulation 7/9/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 7/9/2024 Partial Approval THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 7/9/2024 Approved THOMAS LOGRASSO
Shower Pan 7/9/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/30/2024 Approved THOMAS LOGRASSO
Drywall Nailing 7/30/2024 Approved THOMAS LOGRASSO
Insulation 7/30/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/30/2024 Partial Approval THOMAS LOGRASSO
Underground Mechanical 8/1/2024 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 9/17/2024 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 10/8/2024 Approved THOMAS LOGRASSO
Service/Power Release 10/8/2024 Approved THOMAS LOGRASSO
Final 11/25/2024 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 11/25/2024 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 11/25/2024 Approved THOMAS LOGRASSO