10319 1/2 N ELDORA AVE 91040
Certificate Information: 10319 1/2 N ELDORA AVE 91040
- Application / Permit
- 23014-20000-05185
- Plan Check / Job No.
- B23VN17324
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 20'-2" X 18'-4" CARPORT TO 1 ADU, AND A 25'-0" X 16'-10" 2ND ADU ADDITION INTO 2 DETACHED ADU'S PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK PER ENG.
- Permit Issued
- Issued on 6/21/2024
- Issuing Office
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/24/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/21/2024 | LUISANGEL VALENZUELA |
| Issued | 6/21/2024 | APPLICANT |
| CofO in Progress | 8/4/2025 | DAVID ANDERSON |
| CofO in Progress | 8/12/2025 | DAVID ANDERSON |
| CofO in Progress | 8/13/2025 | DAVID ANDERSON |
| Permit Finaled | 8/26/2025 | RUBEN SALAS |
| CofO Issued | 8/26/2025 | RUBEN SALAS |
| Permit Finaled | 8/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2024 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 1/18/2024 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | NIKKI ZULUETA |
| Grading Pre-Inspection | Cleared | 1/25/2024 | CHARLES POWELL |
| Sewer availability | Cleared | 1/25/2024 | NIKKI ZULUETA |
Contact Information
| Contractor | Build Tuff Construction; Lic. No.: 1076283-B | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: NA92714 | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/31/2024 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 1/7/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/7/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 1/14/2025 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/14/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/10/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Partial Approval | DAVID ANDERSON |
| HVAC-Rough | 4/10/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 4/10/2025 | Approved | DAVID ANDERSON |
| Sewer | 4/10/2025 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 4/14/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 4/14/2025 | Approved | DAVID ANDERSON |
| Sewer | 4/14/2025 | Approved | DAVID ANDERSON |
| Insulation | 4/21/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 4/29/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/29/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 4/29/2025 | Approved | MICHAEL CORTEZ |
| Underground Mechanical | 6/10/2025 | Approved | DAVID ANDERSON |
| Final | 7/23/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 7/23/2025 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Not Required | WILLIAM WREN |
| Smoke Detectors | 7/23/2025 | Approved | WILLIAM WREN |
| Final | 8/1/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 8/1/2025 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 8/12/2025 | Corrections Issued | DAVID ANDERSON |
| Final | 8/13/2025 | OK to Issue CofO | DAVID ANDERSON |