1734 N OGDEN DR 90046

Certificate Information: 1734 N OGDEN DR 90046

Application / Permit
23014-20000-05177
Plan Check / Job No.
B23VN17297
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO CREATE 2-STORY (61'-9" X 51'-5" IRR SHAPE) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NFPA 13R FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 6/10/2025
Issuing Office
Valley
Current Status
Issued on 6/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/18/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 VAHAN JIVALAGIAN
Corrections Issued 1/14/2024 VAHAN JIVALAGIAN
Quality Review Completed 1/17/2024 OMID HEDAYAT
Building Plans Picked Up 1/23/2024 APPLICANT
Applicant returned to address corrections 6/2/2025 VAHAN JIVALAGIAN
Plan Check Approved 6/10/2025 VAHAN JIVALAGIAN
Issued 6/10/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/21/2024 CELINA MORENO
BHO/Hillside ordinance Cleared 5/21/2024 CELINA MORENO
BHO/Hillside ordinance Cleared 5/21/2024 CELINA MORENO
BHO/Hillside ordinance Cleared 5/21/2024 CELINA MORENO
BHO/Hillside ordinance Cleared 5/21/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/30/2024 CELINA MORENO
Sewer availability Cleared 5/30/2024 CELINA MORENO
Hydrant and Access approval Cleared 7/2/2024 KURT CORRAL
Low Impact Development (LID) Cleared 7/9/2024 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 7/12/2024 JEANIE LAM
Miscellaneous Cleared 2/4/2025 NADER TAVASSOLI
GPI Written Notices Cleared 6/2/2025 VAHAN JIVALAGIAN
Grading Pre-Inspection Cleared 6/2/2025 VAHAN JIVALAGIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/6/2025 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 11/18/2025 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 11/19/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 12/3/2025 Approved ROY SPAULDING
PLUMBING-Rough 12/23/2025 Approved ROY SPAULDING
Sewer 12/23/2025 Approved ROY SPAULDING
Structural Steel Frame 12/23/2025 Partial Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 2/18/2026 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 3/16/2026 Corrections Issued ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 5/18/2026 Approved ROY SPAULDING
HVAC-Rough 5/18/2026 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 5/18/2026 Corrections Issued ROY SPAULDING