13539 W HART ST 91405
Certificate Information: 13539 W HART ST 91405
- Application / Permit
- 23014-20000-05176
- Plan Check / Job No.
- B23VN17293
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (N) 27'-6" x 14'-0" TO EXTEND LIVING ROOM AND (N) 11'-5" x 14'-0" ATTACHED TRELLIS (E) S.F.D. PER ENGINEERING.
- Permit Issued
- Issued on 12/20/2023
- Issuing Office
- Current Status
- CofO Issued on 10/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2023 | ALFRED RAMIREZ |
| Corrections Issued | 12/18/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 12/20/2023 | MIROOSH KHACHATOORIAN |
| Issued | 12/20/2023 | APPLICANT |
| CofO in Progress | 9/23/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/9/2024 | DANIEL ORRANTE |
| CofO Issued | 10/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/18/2023 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2023 | CARLOS RAMIREZ |
| Tract Map conditions | Cleared | 12/19/2023 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: C69935 | 16873 MCKEEVER ST GRANADA HILLS, CA 91344 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 5/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 5/23/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/19/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/19/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 7/19/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/19/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/19/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 7/24/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/30/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 9/5/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/5/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 9/5/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/5/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/5/2024 | Approved | OGANES TARAKHCHYAN |