7353-7355 N AMESTOY AVE 91406
Certificate Information: 7353-7355 N AMESTOY AVE 91406
- Application / Permit
- 23014-20000-05163
- Plan Check / Job No.
- B23VN17272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & NEW ADDITION TO (E) SINGLE FAMILY DWELLING (175 SF), DEMO (E) PATIO COVER, AND CONVERT (E) ATT. GARAGE W/ (N) IRR SHAPED 2-STORY ADDITION TO (N) ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33(c) and (e)]
- Permit Issued
- Issued on 3/26/2024
- Issuing Office
- Current Status
- Issued on 3/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | SEAN SHAHMIRI |
| Corrections Issued | 1/16/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 1/18/2024 | STEVEN KIM |
| Applicant returned to address corrections | 3/15/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 3/18/2024 | SEAN SHAHMIRI |
| Issued | 3/26/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/26/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 2/10/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 3/5/2024 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/6/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/13/2024 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 5/17/2024 | No Access for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 5/20/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 6/7/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Wood Construction | 8/7/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 9/3/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Approved | RAUL OLAGI |
| HVAC-Rough | 9/3/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 9/3/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/18/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 9/18/2024 | Partial Approval | RAUL OLAGI |
| HVAC-Rough | 9/18/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/18/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 9/18/2024 | Approved | RAUL OLAGI |
| Insulation | 10/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Insulation | 10/8/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 10/15/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Drywall Nailing | 10/22/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 10/22/2024 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 10/28/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 2/7/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 9/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Final | 9/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 9/18/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Final | 9/18/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Final | 9/18/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 9/18/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Smoke Detectors | 9/18/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 4/16/2026 | Approved | ROBERTO PALACIOS-LOPEZ |