6238 N AUCKLAND AVE 91606

Certificate Information: 6238 N AUCKLAND AVE 91606

Application / Permit
23014-20000-05150
Plan Check / Job No.
B23VN17198
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 12'-0" x 18'-0" ATTACHED PATIO COVER FROM (E) DETACHED GARAGE. ADD 17'-6" x 13'-7" TO AND CONVERT (E) DETACHED 18'-0" x 16'-0" GARAGE INTO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 3/7/2024
Issuing Office
Current Status
CofO Issued on 10/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2023 APPLICANT
Assigned to Plan Check Engineer 12/19/2023 MIROOSH KHACHATOORIAN
Corrections Issued 12/19/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/1/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 2/28/2024 SARKIS HARABEDIAN
Issued 3/7/2024 APPLICANT
CofO in Progress 10/2/2024 JOSE AVILA
CofO Issued 10/8/2024 DANIEL ORRANTE
Permit Finaled 10/8/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/20/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 12/20/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/21/2023 COLIN LOREDO
Sewer availability Cleared 12/21/2023 COLIN LOREDO

Contact Information

Contractor Adar Builders Inc; Lic. No.: 1051859-B       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/1/2024 Partial Approval JOHN HAYES
Underground Mechanical 4/1/2024 Approved JOHN HAYES
Deputy Drilled-In Anchors 4/2/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 4/3/2024 Approved JOHN HAYES
Gas Test 4/3/2024 Approved JOHN HAYES
Underground Mechanical 4/3/2024 Partial Approval JOHN HAYES
Deputy Reinf. Concrete 4/10/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 4/29/2024 Not Ready for Inspection JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 4/29/2024 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 4/29/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/14/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 5/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 5/14/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 5/17/2024 Conditional Approval JOSE AVILA
Rough-Elec/Plmb/HVAC 5/17/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 5/22/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 5/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 5/22/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 5/24/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 5/24/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 6/5/2024 Partial Approval JOSE AVILA
Interior/Exterior Lathing 6/5/2024 Approved JOSE AVILA
Drywall Nailing 6/12/2024 Partial Approval JOSE AVILA
Insulation 6/12/2024 Approved JOSE AVILA
Interior/Exterior Lathing 6/12/2024 Approved JOSE AVILA
Drywall Nailing 6/14/2024 Approved JOSE AVILA
Special/Order Compliance 7/2/2024 Approved JOSE AVILA
ELECTRICAL-Final 9/10/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 9/10/2024 Approved JOSE AVILA
HVAC-Final 9/10/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/10/2024 SGSOV Not Ready JOSE AVILA
Smoke Detectors 9/10/2024 Approved JOSE AVILA
Final 9/25/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 10/1/2024 Approved JOSE AVILA
HVAC-Final 10/1/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved JOSE AVILA
Service/Power Release 10/1/2024 Approved JOSE AVILA
Final 10/2/2024 OK to Issue CofO JOSE AVILA