6238 N AUCKLAND AVE 91606
Certificate Information: 6238 N AUCKLAND AVE 91606
- Application / Permit
- 23014-20000-05150
- Plan Check / Job No.
- B23VN17198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 12'-0" x 18'-0" ATTACHED PATIO COVER FROM (E) DETACHED GARAGE. ADD 17'-6" x 13'-7" TO AND CONVERT (E) DETACHED 18'-0" x 16'-0" GARAGE INTO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 3/7/2024
- Issuing Office
- Current Status
- CofO Issued on 10/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 12/19/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 2/1/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 2/28/2024 | SARKIS HARABEDIAN |
| Issued | 3/7/2024 | APPLICANT |
| CofO in Progress | 10/2/2024 | JOSE AVILA |
| CofO Issued | 10/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 12/20/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 12/21/2023 | COLIN LOREDO |
Contact Information
| Contractor | Adar Builders Inc; Lic. No.: 1051859-B | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2024 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 4/1/2024 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 4/2/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 4/3/2024 | Approved | JOHN HAYES |
| Gas Test | 4/3/2024 | Approved | JOHN HAYES |
| Underground Mechanical | 4/3/2024 | Partial Approval | JOHN HAYES |
| Deputy Reinf. Concrete | 4/10/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 4/29/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 4/29/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 4/29/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/14/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 5/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/17/2024 | Conditional Approval | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 5/17/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 5/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 5/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/24/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 5/24/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/5/2024 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 6/5/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 6/12/2024 | Partial Approval | JOSE AVILA |
| Insulation | 6/12/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 6/12/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 6/14/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 7/2/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 9/10/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 9/10/2024 | Approved | JOSE AVILA |
| HVAC-Final | 9/10/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Not Ready | JOSE AVILA |
| Smoke Detectors | 9/10/2024 | Approved | JOSE AVILA |
| Final | 9/25/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 10/1/2024 | Approved | JOSE AVILA |
| HVAC-Final | 10/1/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 10/1/2024 | Approved | JOSE AVILA |
| Final | 10/2/2024 | OK to Issue CofO | JOSE AVILA |