6020 N CARTWRIGHT AVE 91606
Certificate Information: 6020 N CARTWRIGHT AVE 91606
- Application / Permit
- 23014-20000-05131
- Plan Check / Job No.
- B23VN13005
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF AN EXISTING DETACHED 2-CAR GARAGE (360 SQFT) INTO 1 CAR GARAGE (280 SQFT) AND 80 SQFT ADU W/NEW 2ND STORY ADDITION TO THE ADU (215 SQFT) PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Current Status
- Issued on 11/12/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | PETER MOSESIAN |
| Corrections Issued | 12/14/2023 | PETER MOSESIAN |
| Quality Review Completed | 12/19/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/14/2024 | PETER MOSESIAN |
| Applicant returned to address corrections | 6/11/2024 | PETER MOSESIAN |
| Applicant returned to address corrections | 7/26/2024 | PETER MOSESIAN |
| Plan Check Approved | 8/1/2024 | PETER MOSESIAN |
| Plan Check Approved | 8/7/2024 | INTERNET PERMIT |
| No Progress | 10/25/2024 | INTERNET PERMIT |
| Plan Check Approved | 11/12/2024 | PETER MOSESIAN |
| Issued | 11/12/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/6/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/6/2024 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 5/1/2024 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 5/1/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 6/5/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: NA68803 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 11/14/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/16/2024 | Approved | JOSE AVILA |
| Wood Frame | 12/18/2024 | Approved | JOSE AVILA |
| Wood Frame | 12/24/2024 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 2/4/2025 | Not Ready for Inspection | JOSE AVILA |
| Underground Mechanical | 2/19/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 3/6/2025 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 3/10/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 3/10/2025 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 3/10/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 3/24/2025 | Approved | JOSE AVILA |
| Shower Pan | 3/24/2025 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/25/2025 | Approved | JOSE AVILA |
| Insulation | 3/26/2025 | Not Ready for Inspection | JOSE AVILA |
| Insulation | 4/3/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 4/3/2025 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 4/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 4/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/21/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 4/29/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 12/10/2025 | Approved | JOSE AVILA |
| Final | 12/22/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 12/22/2025 | Approved | JOSE AVILA |