20801 W RINALDI ST 91311

Certificate Information: 20801 W RINALDI ST 91311

Application / Permit
23014-20000-05124
Plan Check / Job No.
B23VN17116
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(18) School Building
Work Description
EPLAN ADDITION (77'0" x 195'4") OF A 2-STORY OVER 1 BASEMENT LEVEL , TYPE 1A CONSTRUCTION TO EXISTING SCHOOL BUILDING. ADDITION TO CONSIST OF THE MAIN AUDITORIUM SPACE, ART, DANCE AND MUSIC CLASSROOMS AND A "SET-BUILDING" WORKSHOP.
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
Issued on 3/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/9/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 PRANITA SHAH
Assigned to Zoning Architect 1/18/2024 PRANITA SHAH
Corrections Issued 2/1/2024 PRANITA SHAH
Quality Review Completed 2/16/2024 GARO TELMI
Applicant returned to address corrections 7/17/2024 PRANITA SHAH
Applicant returned to address corrections 10/1/2024 PRANITA SHAH
Applicant returned to address corrections 10/25/2024 PRANITA SHAH
Applicant returned to address corrections 11/19/2024 PRANITA SHAH
Plan Check Approved 2/27/2025 PRANITA SHAH
Issued 3/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/2/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/2/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/2/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/2/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/2/2024 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 3/2/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/4/2024 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/12/2024 GILBERT URREA
DAS Clearance Cleared 6/17/2024 Eugene Barbeau
Low Impact Development (LID) Cleared 7/19/2024 MARTIN FRAGOSO
City Hist. Cultural Monument Cleared 9/30/2024 LAMBERT GIESSINGER
Historic monument Cleared 9/30/2024 LAMBERT GIESSINGER
Miscellaneous Cleared 10/1/2024 MAYELA VILLA
Tract Map conditions Cleared 10/1/2024 MAYELA VILLA
ZA Case Cleared 10/1/2024 MAYELA VILLA
"T" removal Cleared 10/3/2024 MAYELA VILLA
Green Code Cleared 10/3/2024 AARON COSTA
Miscellaneous Cleared 10/3/2024 MAYELA VILLA
Miscellaneous Cleared 10/3/2024 MAYELA VILLA
Construction within easement Cleared 12/4/2024 THERESA NGUYEN
Fire Marshal Fire Life Safety Cleared 2/6/2025 ANDREW KO
GPI Written Notices Cleared 2/26/2025 PRANITA SHAH
Grading Pre-Inspection Cleared 2/26/2025 PRANITA SHAH
Zoning Plan Check Cleared 2/26/2025 Eugene Barbeau
Hold Cleared 3/28/2025 CARMEN MERAZ

Contact Information

Architect Masotta,, John Joseph; Lic. No.: NA24805       ,
Contractor Del Amo Construction Llc; Lic. No.: 744458-B       ,
Engineer Cuthbert,, Mary; Lic. No.: S5578 700 SOUTH FLOWER ST STE 2100      LOS ANGELES, CA 90017
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012

Inspector Information

No Data Available.

Pending Inspections

Excavation/Setback/Form/Re-Bar 6/10/2026   

Inspection Request History

Pre-Inspection 5/6/2025 Partial Inspection DEANDRE HOFFMAN
Deputy Reinf. Concrete 6/2/2025 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 6/3/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 6/5/2025 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Concrete 6/27/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/30/2025 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 6/30/2025 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 6/30/2025 Partial Inspection GREGORY POMISH
Deputy Reinf. Concrete 7/1/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/10/2025 Approved DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 7/10/2025 Partial Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 7/21/2025 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 7/28/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 8/8/2025 Conditional Approval DEANDRE HOFFMAN
Reinforced Concrete Frame 8/8/2025 Partial Approval DEANDRE HOFFMAN
Special/Order Compliance 8/13/2025 Partial Inspection DEANDRE HOFFMAN
Special/Order Compliance 8/18/2025 Not Ready for Inspection DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 8/20/2025 Corrections Issued DEANDRE HOFFMAN
Notice of Violation 9/2/2025 Not Required DEANDRE HOFFMAN
Special/Order Compliance 9/2/2025 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 10/24/2025 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 10/27/2025 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 10/29/2025 Partial Approval MARTIN TAVITIAN
Deputy Reinf. Concrete 12/17/2025 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/18/2025 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/22/2025 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 1/7/2026 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 1/9/2026 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 1/9/2026 Partial Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 1/14/2026 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 1/28/2026 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 1/28/2026 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 1/28/2026 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/9/2026 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 2/24/2026 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/2/2026 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/5/2026 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/13/2026 Partial Approval EDWIN GREGORYONA
Deputy Steel/Welding 4/27/2026 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 4/27/2026 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 5/4/2026 Partial Approval EDWIN GREGORYONA
Reinforced Masonry Frame 5/8/2026 Partial Approval EDWIN GREGORYONA