4343 N ELMER AVE 91602

Certificate Information: 4343 N ELMER AVE 91602

Application / Permit
23014-20000-05111
Plan Check / Job No.
B23VN17029
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
5'-6" x 7'-3" AND 15' X 23'-1" ADDITIONS AND MAJOR REMODEL. ADD 3'-3" x 6' FRONT PORCH. NFPA-13D FIRE SPRINKLER REQUIRED THROUGHOUT.
Permit Issued
Issued on 1/8/2024
Issuing Office
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 12/15/2023 SERGIO MUNIZ
Corrections Issued 12/16/2023 SERGIO MUNIZ
Building Plans Picked Up 12/22/2023 APPLICANT
Applicant returned to address corrections 1/3/2024 SERGIO MUNIZ
Applicant returned to address corrections 1/5/2024 ISIS ARGUETA
Issued 1/8/2024 APPLICANT
CofO in Progress 11/6/2024 CHRISTOPHER ROJAS
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

ZI Cleared 12/27/2023 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 12/28/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/28/2023 CARLOS AGUILERA
Sewer availability Cleared 12/28/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/7/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/8/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/26/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 3/26/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/10/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/10/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 5/10/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 5/10/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 5/10/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/10/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/5/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 6/5/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 6/5/2024 Approved CHRISTOPHER ROJAS
Wood Frame 6/5/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Insulation 6/14/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 6/14/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 6/17/2024 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/8/2024 Corrections Issued CHRISTOPHER ROJAS
Shower Pan 7/8/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/11/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 7/18/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/1/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 10/1/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/1/2024 Approved CHRISTOPHER ROJAS
Green Building Final 10/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 10/1/2024 Approved CHRISTOPHER ROJAS
HVAC-Final 10/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Final 10/1/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 10/1/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 10/1/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 10/4/2024 Approved CHRISTOPHER ROJAS
HVAC-Final 10/4/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 10/4/2024 Approved CHRISTOPHER ROJAS
Final 11/6/2024 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 11/6/2024 Approved CHRISTOPHER ROJAS