22123 W VALERIO ST 91303

Certificate Information: 22123 W VALERIO ST 91303

Application / Permit
23014-20000-05108
Plan Check / Job No.
B23VN17010
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITITION OF 21'-0" x 17'-0" TO CREATE NEW BEDROOM TO (E) S.F.D. PER ENGINEERING
Permit Issued
Issued on 1/8/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 12/12/2023 ALFRED RAMIREZ
Corrections Issued 12/12/2023 ALFRED RAMIREZ
Plan Check Approved 12/29/2023 LUISANGEL VALENZUELA
Issued 1/8/2024 APPLICANT
CofO in Progress 8/8/2024 JEFFREY HARTLINE
Permit Finaled 8/14/2024 JOHN JANSON
CofO Issued 8/14/2024 JOHN JANSON
Permit Finaled 8/14/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/15/2023 EDGAR ALCARAZ
Sewer availability Cleared 12/15/2023 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 12/18/2023 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/25/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 2/23/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 2/23/2024 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 4/10/2024 Corrections Issued CHRIS CHRISTENSEN
Wood Frame 4/10/2024 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/26/2024 No Access for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/30/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/31/2024 Approved CHRIS CHRISTENSEN
Wood Frame 5/31/2024 Approved CHRIS CHRISTENSEN
Insulation 6/4/2024 Approved CHRIS CHRISTENSEN
Drywall Nailing 6/14/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 6/14/2024 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/5/2024 Approved JEFFREY HARTLINE
Final 8/5/2024 Corrections Issued JEFFREY HARTLINE
Green Building Final 8/5/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 8/5/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 8/7/2024 Approved JEFFREY HARTLINE
Final 8/7/2024 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 8/7/2024 Approved JEFFREY HARTLINE
PLUMBING-Final 8/7/2024 Approved JEFFREY HARTLINE