7700 N OAK PARK AVE 91406
Certificate Information: 7700 N OAK PARK AVE 91406
- Application / Permit
- 23014-20000-05102
- Plan Check / Job No.
- B23VN16991
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED IRR SHAPED 18'-0"X7'-4" ADDN W/ INT & EXT REMODEL TO EX 1-STORY SFD W/ ATT GARAGE. CONSTRUCTION DESIGN PER ENGR. "COMPLY WITH DEPARTMENT ORDER effective date 08/01/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 12/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 12/17/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 1/3/2024 | APPLICANT |
| Applicant returned to address corrections | 3/7/2024 | KAMYAR EMAMI |
| Issued | 10/4/2024 | APPLICANT |
| CofO in Progress | 12/8/2025 | MICKEY YAMASHITA |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/5/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 9/24/2024 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 9/25/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28531 PALOS VERDES DR EAST RANCHO PALOS VERDES, CA 90275 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/5/2024 | Partial Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/14/2024 | Approved | LEO MILBAUER |
| Footing/Foundation/Slab | 11/14/2024 | Approved | LEO MILBAUER |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Corrections Issued | MICKEY YAMASHITA |
| Wood Frame | 4/3/2025 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 4/22/2025 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 4/22/2025 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 4/22/2025 | Partial Approval | MICKEY YAMASHITA |
| Wood Frame | 4/22/2025 | Not Ready for Inspection | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 5/13/2025 | Conditional Approval | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 5/13/2025 | Approved | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 5/13/2025 | Partial Approval | MICKEY YAMASHITA |
| HVAC-Rough | 5/13/2025 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 5/13/2025 | Corrections Issued | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 6/2/2025 | Conditional Approval | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 6/2/2025 | Not Ready for Inspection | MICKEY YAMASHITA |
| Green Building Rough | 6/2/2025 | Approved | MICKEY YAMASHITA |
| HVAC-Rough | 6/2/2025 | Approved | MICKEY YAMASHITA |
| Insulation | 6/2/2025 | Approved | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 6/2/2025 | Partial Approval | MICKEY YAMASHITA |
| PLUMBING-Rough | 6/2/2025 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 7/17/2025 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 7/17/2025 | Approved | MICKEY YAMASHITA |
| PLUMBING-Rough | 7/17/2025 | Approved | MICKEY YAMASHITA |
| Shower Pan | 7/17/2025 | Corrections Issued | MICKEY YAMASHITA |
| Drywall Nailing | 11/26/2025 | Approved | MICKEY YAMASHITA |
| Final | 11/26/2025 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Final | 11/26/2025 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | MICKEY YAMASHITA |
| Shower Pan | 11/26/2025 | Approved | MICKEY YAMASHITA |
| Smoke Detectors | 11/26/2025 | Corrections Issued | MICKEY YAMASHITA |
| Final | 12/2/2025 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 12/2/2025 | Approved | MICKEY YAMASHITA |
| Smoke Detectors | 12/2/2025 | Not Ready for Inspection | MICKEY YAMASHITA |
| ELECTRICAL-Final | 12/8/2025 | Approved | MICKEY YAMASHITA |
| Final | 12/8/2025 | OK to Issue CofO | MICKEY YAMASHITA |
| HVAC-Final | 12/8/2025 | Approved | MICKEY YAMASHITA |
| PLUMBING-Final | 12/8/2025 | Approved | MICKEY YAMASHITA |
| Smoke Detectors | 12/8/2025 | Approved | MICKEY YAMASHITA |