336 N EDINBURGH AVE 90048
Certificate Information: 336 N EDINBURGH AVE 90048
- Application / Permit
- 23014-20000-05098
- Plan Check / Job No.
- B23VN16987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and addition to (e) one story SFD, fire sprinkler nfpa 13D
- Permit Issued
- Issued on 8/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2023 | RAMA DABADGE |
| Corrections Issued | 12/14/2023 | RAMA DABADGE |
| Building Plans Picked Up | 1/18/2024 | APPLICANT |
| Applicant returned to address corrections | 6/25/2024 | SERGIO MUNIZ |
| Plan Check Approved | 7/22/2024 | MOHAMMAD ESMAILI |
| Issued | 8/2/2024 | APPLICANT |
| CofO in Progress | 3/21/2025 | JOSE MACIAS |
| Permit Finaled | 3/23/2025 | DEROLD HAUFF |
| Permit Finaled | 3/23/2025 | DEROLD HAUFF |
| CofO Issued | 3/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2024 | KEVIN AVILA |
| Sewer availability | Cleared | 2/26/2024 | KEVIN AVILA |
| Low Impact Development (LID) | Cleared | 6/21/2024 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/11/2024 | WALLIE JONG |
Contact Information
| Contractor | Superior Home Builders Inc; Lic. No.: 875933-B | 6569 CLEOMOORE AVE WEST HILLS, CA 91307 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/5/2024 | Conditional Approval | JOSE MACIAS |
| Deputy Drilled-In Anchors | 9/13/2024 | Conditional Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 9/17/2024 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 9/17/2024 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 9/17/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/24/2024 | Approved | JOSE MACIAS |
| Wood Frame | 9/24/2024 | Approved | JOSE MACIAS |
| Insulation | 9/27/2024 | Approved | JOSE MACIAS |
| Wood Frame | 9/30/2024 | Approved | JOSE MACIAS |
| Deputy Wood Construction | 10/16/2024 | No Access for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/23/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 10/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 10/23/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 10/23/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 10/31/2024 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | JOSE MACIAS |
| Green Building Rough | 11/15/2024 | Approved | JOSE MACIAS |
| Insulation | 11/15/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 11/15/2024 | Approved | JOSE MACIAS |
| Drywall Nailing | 11/25/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 11/25/2024 | Approved | JOSE MACIAS |
| Shower Pan | 11/25/2024 | Approved | JOSE MACIAS |
| Final | 3/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Final | 3/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 3/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| Final | 3/13/2025 | OK to Issue CofO | JOSE MACIAS |
| Green Building Final | 3/13/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 3/13/2025 | Approved | JOSE MACIAS |