11653 W MARGATE ST 91601

Certificate Information: 11653 W MARGATE ST 91601

Application / Permit
23014-20000-05095
Plan Check / Job No.
B23VN16972
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 11'-6" x 9'-1" ADDITION TO AND CONVERT 15'-5" x 18'-0" PORTION OF (E) DET GARAGE TO (N) 356 SF A.D.U PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). THE REMAINING 4'-7" x 18'-0" OF (E) DET GARAGE TO BE CONVERTED TO (N) STORAGE.
Permit Issued
Issued on 5/9/2024
Issuing Office
Current Status
CofO Issued on 11/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2023 APPLICANT
Assigned to Plan Check Engineer 12/29/2023 LUISANGEL VALENZUELA
Corrections Issued 1/1/2024 LUISANGEL VALENZUELA
Plan Check Approved 5/8/2024 SARKIS HARABEDIAN
Issued 5/9/2024 APPLICANT
CofO in Progress 11/2/2024 JUAN VALENZUELA
Permit Finaled 11/13/2024 DANIEL ORRANTE
CofO Issued 11/13/2024 DANIEL ORRANTE
Permit Finaled 11/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/3/2024 LEE GUILBEAUX
Miscellaneous Cleared 1/3/2024 BRENNEN OBETO
Roof/Waste drainage to street Cleared 1/3/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/4/2024 LEE GUILBEAUX
Sewer availability Cleared 1/4/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/4/2024 LEE GUILBEAUX
Specific Plan Cleared 1/19/2024 JOANNA MARROQUIN
ZI Cleared 1/19/2024 JOANNA MARROQUIN
ZI Cleared 1/19/2024 JOANNA MARROQUIN
Construction near power lines Cleared 4/29/2024 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor My Home Builders Inc; Lic. No.: 1002927-B       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 6/10/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval CHRISTOPHER ROJAS
Sewer 6/26/2024 Approved SALVADOR MARTINEZ
Rough-Elec/Plmb/HVAC 6/27/2024 No Access for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/1/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/1/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/11/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 7/11/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 7/11/2024 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 7/11/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Underground Mechanical 7/11/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/17/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 7/17/2024 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 7/17/2024 Approved CHRISTOPHER ROJAS
Insulation 7/23/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/23/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 7/29/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/31/2024 Approved CHRISTOPHE COCHRAN
Shower Pan 7/31/2024 Approved CHRISTOPHE COCHRAN
Final 10/22/2024 Corrections Issued JUAN VALENZUELA
Green Building Final 10/22/2024 Approved JUAN VALENZUELA
MERV13>=Final 10/22/2024 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 10/22/2024 Corrections Issued JUAN VALENZUELA
Final 10/30/2024 OK to Issue CofO JUAN VALENZUELA
Smoke Detectors 10/30/2024 Approved JUAN VALENZUELA