2030 S FOX HILLS DR 90025
Certificate Information: 2030 S FOX HILLS DR 90025
- Application / Permit
- 23014-20000-05086
- Plan Check / Job No.
- B23VN16952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story addition of 27' x 13' 2" in the south east of the lot to the SFD, and one story addition of 14' x 24' 6" in the north east of the lot to the SFD with attached Patio cover. NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Valley
- Current Status
- Issued on 6/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2023 | NAREG ATARIAN |
| Corrections Issued | 12/24/2023 | NAREG ATARIAN |
| Quality Review Completed | 12/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 1/8/2024 | APPLICANT |
| Applicant returned to address corrections | 6/3/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 6/17/2024 | NAREG ATARIAN |
| Plan Check Approved | 6/26/2024 | NAREG ATARIAN |
| Issued | 6/26/2024 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/26/2024 | DANIEL CORONADO |
| Low Impact Development (LID) | Cleared | 5/21/2024 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 5/28/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 6/5/2024 | KIMBERLY HERNANDEZ |
| GPI Written Notices | Cleared | 6/26/2024 | MATTHEW JENKINS |
| Grading Pre-Inspection | Cleared | 6/26/2024 | MATTHEW JENKINS |
Contact Information
| Contractor | Mackey Construction And Restoration; Lic. No.: 761277-B | 5739 KANAN ROAD #373 AGOURA HILLS, CA 91301 |
| Engineer | Rodgers,, Rob J; Lic. No.: S4339 | 4539 BECK AVE STUDIO CITY, CA 91602 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 8/14/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 8/15/2024 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/21/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/26/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 8/27/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/1/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 12/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 1/21/2025 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 1/21/2025 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/6/2025 | Partial Approval | SEAN HAUPT |
| ELECTRICAL-Rough | 2/14/2025 | Corrections Issued | SEAN HAUPT |
| HVAC-Rough | 2/14/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 2/27/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 2/27/2025 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/6/2025 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 3/18/2025 | Not Ready for Inspection | DANIEL VERA |
| Shower Pan | 3/21/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 3/28/2025 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/6/2025 | Approved | EVAN COOPER |
| Gas Test | 7/24/2025 | Approved | DANIEL VERA |
| PLUMBING-Rough | 7/24/2025 | Not Ready for Inspection | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 9/19/2025 | Partial Approval | DANIEL VERA |
| PLUMBING-Rough | 9/19/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 10/8/2025 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/8/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 10/8/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 10/8/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/8/2025 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 10/8/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 10/20/2025 | Corrections Issued | DANIEL VERA |
| Insulation | 10/20/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 10/29/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 1/20/2026 | Approved | EVAN COOPER |
| Sewer | 1/20/2026 | Approved | EVAN COOPER |