10317-10317 1/2 N ELDORA AVE 91040
Certificate Information: 10317-10317 1/2 N ELDORA AVE 91040
- Application / Permit
- 23014-20000-05084
- Plan Check / Job No.
- B23VN16941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) 20' X 18' CARPORT WITH 25'3" x 16'5" ADDITION INTO (2) NEW DETACHED ADU'S PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK PER ENGINEER DESIGN.
- Permit Issued
- Issued on 6/21/2024
- Issuing Office
- Current Status
- CofO Issued on 1/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 12/24/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/21/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 6/5/2024 | MIROOSH KHACHATOORIAN |
| Issued | 6/21/2024 | APPLICANT |
| CofO in Progress | 12/19/2024 | DAVID ANDERSON |
| CofO in Progress | 1/3/2025 | DAVID ANDERSON |
| CofO in Progress | 1/3/2025 | DAVID ANDERSON |
| Permit Finaled | 1/14/2025 | RUBEN SALAS |
| CofO Issued | 1/14/2025 | RUBEN SALAS |
| Permit Finaled | 1/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2024 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 1/17/2024 | COLIN LOREDO |
| Sewer availability | Cleared | 1/17/2024 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2024 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 1/24/2024 | CHARLES POWELL |
Contact Information
| Contractor | Build Tuff Construction; Lic. No.: 1076283-B | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: NA92714 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 7/22/2024 | Partial Approval | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 7/25/2024 | Conditional Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 7/31/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/14/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 8/14/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 8/14/2024 | Approved | DAVID ANDERSON |
| Insulation | 8/21/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/21/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 8/29/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 10/17/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Sewer | 10/17/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/17/2024 | Partial Approval | DAVID ANDERSON |
| Footing/Foundation/Slab | 10/21/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 10/21/2024 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/28/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 10/28/2024 | Partial Approval | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/20/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Final | 11/27/2024 | Corrections Issued | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 11/27/2024 | SGSOV Not Required | DAVID ANDERSON |
| Smoke Detectors | 11/27/2024 | Approved | DAVID ANDERSON |
| Final | 12/6/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 12/9/2024 | Corrections Issued | DAVID ANDERSON |
| Final | 12/18/2024 | OK to Issue CofO | DAVID ANDERSON |