ePlan: (N) ADDITION TO (E) SFD, (N) FRONT PATIO COVER TO SFD, (N) REAR PATIO COVER TO SFD, AND INTERIOR REMODEL OF SFD
Permit Issued
Issued on 4/3/2024
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2023 APPLICANT
Assigned to Plan Check Engineer 12/15/2023 JOHNPAUL ISIP
Corrections Issued 12/18/2023 JOHNPAUL ISIP
Applicant returned to address corrections 2/28/2024 CAROLEAN BASMA
Plan Check Approved 3/5/2024 CAROLEAN BASMA
Issued 4/3/2024 APPLICANT
CofO in Progress 1/21/2025 JAVIER RAMOS JR
Permit Finaled 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 1/4/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/5/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 2/14/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/14/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/22/2024 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 5/2/2024 Conditional Approval JAVIER RAMOS JR
Footing/Foundation/Slab 5/6/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 5/6/2024 Partial Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 5/30/2024 Partial Inspection JAVIER RAMOS JR
Pre-Inspection 5/30/2024 Approved JAVIER RAMOS JR
Deputy Drilled-In Anchors 6/13/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/18/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/28/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 8/28/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 8/28/2024 Approved JAVIER RAMOS JR
Green Building Rough 8/28/2024 Approved JAVIER RAMOS JR
HVAC-Rough 8/28/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/28/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 8/28/2024 Approved JAVIER RAMOS JR
Sewer 8/28/2024 Approved JAVIER RAMOS JR
Insulation 9/4/2024 Approved JOSE AVILA
Special/Order Compliance 9/4/2024 Corrections Issued JOSE AVILA
Drywall Nailing 9/10/2024 Corrections Issued SALVADOR MARTINEZ
Shower Pan 9/10/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 9/12/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/12/2024 Approved JAVIER RAMOS JR
Wood Frame 9/12/2024 Not Ready for Inspection JAVIER RAMOS JR
Wood Frame 10/11/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/20/2024 Approved JAVIER RAMOS JR
Final 11/20/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 11/20/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/20/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 11/20/2024 Approved JAVIER RAMOS JR
Final 1/21/2025 OK to Issue CofO JAVIER RAMOS JR