20137 W LABRADOR ST 91311

Certificate Information: 20137 W LABRADOR ST 91311

Application / Permit
23014-20000-05033
Plan Check / Job No.
B23VN16791
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to new two story 21' x 31'ADU per LAMC 12.22 A.33 (c)* and (d)*. All work done per engineer.
Permit Issued
Issued on 4/11/2024
Issuing Office
Valley
Current Status
Issued on 4/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/7/2023 APPLICANT
Assigned to Plan Check Engineer 12/21/2023 NAREG ATARIAN
Corrections Issued 12/24/2023 NAREG ATARIAN
Quality Review Completed 12/28/2023 OMID HEDAYAT
Building Plans Picked Up 1/3/2024 APPLICANT
Plan Check Approved 4/10/2024 NAREG ATARIAN
Issued 4/11/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/5/2024 EDGAR ALCARAZ
Sewer availability Cleared 1/16/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 2/21/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 3/25/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/27/2024 EDGAR ALCARAZ
Construction near power lines Cleared 4/1/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Segovia,, Felipe; Lic. No.: C41102 2622 DORSET DR      TORRANCE, CA 90503

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/24/2024 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 4/29/2024 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 4/30/2024 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/15/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 6/14/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/24/2024 Approved DAVID SCANTLIN
Green Building Rough 6/24/2024 Approved DAVID SCANTLIN
Insulation 6/24/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 6/24/2024 Partial Approval DAVID SCANTLIN
Shower Pan 6/24/2024 Approved DAVID SCANTLIN
Drywall Nailing 7/1/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 7/1/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 8/22/2024 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 8/22/2024 Approved DAVID SCANTLIN
Final 10/3/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 10/3/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 10/3/2024 Approved DAVID SCANTLIN
Final 5/6/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 5/6/2026 Approved JACK KARGODORIAN
Final 5/29/2026 Corrections Issued JACK KARGODORIAN
Final 6/3/2026 Corrections Issued JACK KARGODORIAN