2014 N MOUNT OLYMPUS DR 90046

Certificate Information: 2014 N MOUNT OLYMPUS DR 90046

Application / Permit
23014-20000-04998
Plan Check / Job No.
B23VN16717
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 1ST FLOOR ADDITION (144 SQFT) AND 2ND STORY ADDITION (2231 SQFT) W/COVERED DECK/REAR PATIO/FRONT PORCH (936 SQFT) TO THE EXISTING 1-STORY SINGLE FAMILY DWELLING W/NFPA 13D SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 3/14/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 PETER MOSESIAN
Corrections Issued 12/9/2023 PETER MOSESIAN
Quality Review Completed 12/12/2023 OMID HEDAYAT
Building Plans Picked Up 12/14/2023 APPLICANT
Plan Check Approved 3/14/2024 PETER MOSESIAN
Issued 3/14/2024 APPLICANT
CofO in Progress 5/13/2026 ROY SPAULDING
CofO Issued 5/14/2026 DEROLD HAUFF
Permit Finaled 5/14/2026 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 12/27/2023 DAVID URITA
ZA Case Cleared 12/27/2023 DAVID URITA
BHO/Hillside ordinance Cleared 1/2/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 1/2/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 1/2/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 1/2/2024 JEANIE LAM
BHO/Hillside ordinance Cleared 1/2/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/3/2024 JEANIE LAM
Sewer availability Cleared 1/3/2024 JEANIE LAM
Hydrant and Access approval Cleared 2/17/2024 GILBERT URREA
Low Impact Development (LID) Cleared 3/7/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/7/2024 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Geologist Bovenizer,, Ernest; Lic. No.: EG2515 7622 GODDARD AVENUE      LOS ANGELES, CA 90045

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/3/2024 Conditional Approval RAUL BARAJAS
Deputy Drilled-In Anchors 5/7/2024 Conditional Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 5/8/2024 Conditional Approval ROY SPAULDING
Underground Mechanical 5/14/2024 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 5/22/2024 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval RAUL BARAJAS
Green Building Rough 7/25/2024 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 7/25/2024 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 8/14/2024 Conditional Approval BRENDAN MORELLI
BUILDING-Rough-Frame 9/6/2024 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 9/6/2024 Conditional Approval RAUL BARAJAS
Deputy Wood Construction 9/6/2024 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 9/6/2024 Approved RAUL BARAJAS
Green Building Rough 9/6/2024 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 9/6/2024 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/19/2024 Partial Approval ROY SPAULDING
HVAC-Rough 12/19/2024 Partial Approval ROY SPAULDING
PLUMBING-Rough 12/19/2024 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 1/17/2025 Partial Approval ROY SPAULDING
HVAC-Rough 1/17/2025 Partial Approval ROY SPAULDING
PLUMBING-Rough 1/17/2025 Partial Approval ROY SPAULDING
BUILDING-Rough-Frame 2/20/2025 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 2/20/2025 Approved ROY SPAULDING
Green Building Rough 2/20/2025 Approved ROY SPAULDING
HVAC-Rough 2/20/2025 Approved ROY SPAULDING
Verify Sprinkler Sign Off 2/20/2025 Approved ROY SPAULDING
Insulation 3/26/2025 Partial Approval ALEX COLIN
Interior/Exterior Lathing 3/26/2025 Partial Approval ALEX COLIN
Shower Pan 3/26/2025 Approved ALEX COLIN
Insulation 4/2/2025 Approved ROY SPAULDING
Drywall Nailing 5/9/2025 Approved ROY SPAULDING
Interior/Exterior Lathing 5/9/2025 Approved ROY SPAULDING
BUILDING-Rough-Frame 4/10/2026 Approved ROY SPAULDING
Final 4/10/2026 Corrections Issued ROY SPAULDING
Green Building Final 4/10/2026 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/10/2026 SGSOV Approved ROY SPAULDING
Smoke Detectors 4/10/2026 Approved ROY SPAULDING
Final 5/5/2026 OK to Issue CofO ROY SPAULDING